UAE: Force Majeure: A Practical FAQ for Businesses

Status

In force

Issuing Authority

Dubai Department of Economy and Tourism

Please find below a summary of the document prepared by the realLaw AI team.

 

UAE: Force Majeure: A Practical FAQ for Businesses is a practical guidance document prepared for Dubai-based businesses by Dubai Economy & Tourism in partnership with Dubai Chambers and Baker McKenzie. It was published on 26 August 2026 and explains how force majeure, hardship and related contractual concepts operate under UAE law in the context of commercial disruption. 

 

The guide emphasises that force majeure has a specific legal meaning under UAE law and does not cover every unexpected event, delay, increase in costs or adverse commercial development. The central distinction is between an event that makes contractual performance objectively impossible and one that merely makes performance more difficult, delayed, expensive or commercially burdensome. Increased construction costs, inflation, supply-chain delays, changes in shipping routes, higher fuel prices and regional instability therefore do not automatically qualify as force majeure. 

 

A significant part of the guide addresses the transition from the previous UAE Civil Code to the new UAE Civil Transactions Law, Federal Law No. 25 of 2025, which entered into force on 1 June 2026. As a practical starting point, businesses should determine when the relevant contract was entered into. The guide explains that the New Civil Code is generally expected to apply to facts and contracts arising on or after 1 June 2026, while earlier contracts generally remain governed by the previous Civil Code unless otherwise expressly provided. 

 

Under the previous Civil Code, force majeure was principally governed by Article 273. Under the New Civil Code, the corresponding regime is contained in Article 236. The fundamental requirement of impossibility remains, but the new regime provides greater flexibility in cases of partial and temporary impossibility. Where performance becomes totally impossible under a bilateral contract, the corresponding reciprocal obligations are extinguished and the contract is automatically rescinded. In cases of partial impossibility, either party may rely on extinguishment of the corresponding part or seek judicial rescission. For temporary impossibility in continuing contracts, the parties may invoke extinguishment of the corresponding obligation, seek amendment of the contract or apply to the court for rescission. 

 

The guide contrasts this with the previous Article 273 regime, under which complete impossibility generally resulted in automatic rescission, while partial or temporary impossibility generally extinguished the affected part of the obligation, with the remainder continuing unless the creditor exercised the relevant cancellation rights. The New Civil Code therefore gives parties greater ability to select among available remedies in partial or temporary disruption scenarios. uae-force-majeure-guidebook-en

A contractual force majeure clause is not always required in mainland UAE contracts governed by federal law because statutory force majeure rules may apply even where the contract is silent. Where a contract contains an express force majeure clause, however, the wording of that clause is critical. Qualifying events, trigger language, notice requirements, mitigation obligations and contractual consequences may determine whether relief is available. The guide stresses that procedural requirements, particularly notices and updates, can materially affect the success of a force majeure claim. 

 

The guide identifies four cumulative conditions that a party generally needs to establish to invoke force majeure: the event must have been unforeseeable at the time of contracting; its consequences must have been unavoidable despite reasonable mitigation efforts; performance must have become objectively impossible rather than merely difficult or onerous; and there must be direct causation between the event and the inability to perform, without fault on the part of the invoking party. Objective impossibility may be physical, such as a complete closure of transport routes, or legal, such as a binding prohibition, sanction or government order that makes performance unlawful. 

 

Where force majeure is validly established, the affected obligation may be discharged by operation of law. Non-performance of an obligation that has been legally extinguished is generally not treated as a contractual breach, and damages will normally not be recoverable for the period and scope in which performance was impossible. Nevertheless, contractual risk allocation remains relevant, including provisions addressing deposits, advance payments, sunk costs and other financial consequences. 

 

The guide separately addresses payment obligations. Amounts that have already accrued generally remain due and enforceable unless the contract provides otherwise. Businesses facing cash-flow pressure may instead agree revised payment schedules, deferrals, credit notes or other commercial accommodations. Where a fixed, due and undisputed debt is withheld, UAE law also provides a payment-order procedure as an expedited recovery mechanism. 

 

Timing is another important consideration. A party should generally invoke force majeure when performance has become objectively impossible, rather than merely when a disruptive event first arises. Invoking it prematurely may weaken the claim if performance remains possible, while delay in invoking available contractual rights may create additional breach or non-performance risks. The guide recommends using objective evidence such as government suspension orders, airspace or port closures...