47.1 Method Statement Plan/safety procedures in detail with Site Setting Out Plan for the demolition work, including safe use of heavy machine/equipment, certification of cranes & lifting tools, segregation, collection and disposal of construction waste. Personal Protective Equipment shall be provided to the workers.
47.2 The contractor should fill the COC I & II Form & submit to Trakhees Department along with Method Statement Plan.
47.3 NOC from DEWA confirming that all the service lines like electricity and water, etc. are disconnected should be submitted with COC Forms.
47.4 Drainage Layout Drawing of existing area (which needs to be demolished) should be submitted.
47.5 All septic tanks/soak ways/holding tanks/manholes that contain or contained waste liquids should be cleaned and wastes disposed as per PCFC/ DM procedures. Forms for waste disposal are available on our website www.ehss.ae.
47.6 Solid wastes/garbage/debris/construction waste material should be segregated as building material waste/domestic wastes/ hazardous wastes and disposed as per PCFC/DM procedures. Forms for waste disposal are available on our website www.eh...