Trakhees Regulations PS 42.0 Site Office

Status

In force

Issuing Authority

Ports, Customs and Free Zone Corporation

Effective date

XX.XX.XXXX

Official Link

https://

42.1 NOC Letter stating allocation of plot/area with endorsed affection plan for site office from Client/Developer.

 

42.2 Inlet road of the plot should be hard paved and compacted using suitable road based material. Same should showing in relevant drawing(s).

 

42.3 Guidelines: Installation of diesel fired generator (if any) to be followed.

 

42.4 All electrical installations/fittings shall be fitted with ELCB's and properly earth as per DEWA regulations.

 

42.5 Drainage to be installed as per Chapter 3 General Requirement section - of EHS-Trakhees Design & Development Regulations.

 

42.6 Mess/Pantry, Toilet block to be provided with 8-10 air changes per hour.

 

42.7 Site office should be installed in such a manner so that while operating tower crane boom with load should not pass above the site office.

 

42.8 Provision for sanitation/rest room/dining/locker for the worker/staff shall be provided.

 

42.9 COC stage -1 shall be obtained from EHS-Construction Safety prior to the commencement of the project.