Trakhees Regulations PS 25.0 Paint / Blast Booth / Rooms

Status

In force

Issuing Authority

Ports, Customs and Free Zone Corporation

Effective date

XX.XX.XXXX

Official Link

https://

PCFC-Entity (Business Unit) Name: Trakhees-Ports, Customs & Free Zone Corporation

Department Name: Civil Engineering Department (CED)

Section Name: Permits Section (Facilities)

Document Reference Number: PCFC-TRK-CED-PS-REG-25

Revision Number: 01

Revision Date: May 2019

Classification: Public

 

25.1 Spray painting operations/activities in the open area is not permitted. All spray painting operations shall be carried out in the fully covered and proper designed/constructed/approved painting booth/building. The construction material shall be of fire proof material and acceptable & approved by Authority. The walls & flooring shall be of smooth finish to prevent pocketing of paint residue and easily cleanable.

 

25.2 Paint / blast booth/building fitted with proper extraction/filtrations system Design calculation of the same shall be based on ASHRE Standards.

 

25.3 All electrical machine/equipment/lighting/fixtures etc. in the painting booth/building shall be of flame proof/ignition proof type.

 

25.4 Outlet from extraction/filtration system shall be taken out from the building, raised to minimum 3 meter from the roof ridge level...