Trakhees Regulations PS 21.0 Machinery Installation General Requirements

Status

In force

Issuing Authority

Ports, Customs and Free Zone Corporation

Effective date

XX.XX.XXXX

Official Link

https://
PCFC-Entity (Business Unit) Name:Trakhees - Ports, Customs & Free Zone Corporation
Department Name:Civil Engineering Department (CED)

 

21.1 Machinery Layout Plan and dimensions with list of machine/equipment shall be submitted by the licensee/owner of the facility prior to installation. All machinery installation shall comply with applicable EHS-Trakhees-PCFC Guidelines and Regulations.

 

21.2 Full operational details and technical specifications with relevant drawings/brochure/catalogue etc. shall be submitted. Wherever applicable, full technical details/specifications/drawings with test certificates for the installation of Boiler, Heating oven, Furnace, Pressure Vessels, Compressors and Lifting Equipment, shall be submitted for approval prior to installation.

 

21.3 Minimum 1 meter horizontal clearance from the walls/structure to the machine/equipment and minimum 2 meters in-between each machine/equipment shall be maintained.

 

21.4 All service lines & power cables etc. either to be put in covered trenches or routed through elevated cable trays/pipe rack and shall not be laid down directly ...