PCFC- Entity (Business Unit) Name: Trakhees (Dept. of Planning & Development)
Department Name: Civil Engineering Department (CED)
Section Name: Permits (Sustainability)
Document Reference Number: PCFC-TRK-CED-GB-G07
Revision Number: 01
Revision Date: December 2018
Classification: Public
This document is being issued by Trakhees CED – Permit (Sustainability) department in the interest of the stakeholders so that all the collective efforts put in the project can be collated and made part of InHouse Certification Submissions.
Most importantly this document is to provide the stakeholders with a broad perspective of the type of evidence CED’s Sustainability Department expects in the process of review of the submissions for the certifications.
This general guideline is applicable to all the stakeholders involved in the Green building projects within Dubai World business units under the Ports, Customs and Free Zone Corporation (PCFC) that have opted to seek CED’s Certification for the Green Building Projects
The aim of this document is to highlight the importance of supporting documentation and evidence in order to establish the fulfilment of a credit / sustainability initiative in the project. It is important that the project stakeholders comprising the client, consultant, green building specialist and others together are able to demonstrate the compliance to the Regulation and its requirements in a clear and consistent manner. This entails supporting documentation comprising calculations, reports, photographs etc. depending on the nature of the credit.
This guideline is given in the form of a table listing the documentation required as evidence to support the compliance of the credit.
This guideline provides a broad framework of the documentation involved in actual implementation of the green building principles and is intended purely to familiarize the client and the other stakeholders on the need to adequately demonstrate the compliance through several mechanisms.
The table attached below is not meant to serve as an exhaustive and all inclusive list encompassing all the aspects of sustainability. While this serves to throw light on the basic requirements, the stakeholders can exercise their option and judgment in including other forms of evidence that they feel are crucial in demonstrating the compliance.
This guideline does not bind CED (Permit section – Sustainability) in limiting its response to the elements of the table. CED has the right to ask additional information / clarification/documentation that it may feel essential prior to fulfilment of the requirements and award of the credit.
Should you need any assistance please do not hesitate to contact the department.
|
Credit Description |
Credit Reference |
Document Description |
|
SUSTAINABLE SITE |
| |
|
Credit Description |
Credit Reference |
Document Description |
|
|
SSC2 - Option 2 - CC |
List of services available inside the radius (at least 10 basic services) |
|
Credit Description |
Credit Reference |
Document Description |
|
Low-Emission & Fuel Efficient Vehicles |
|
Site photographs showing locations of preferred parking spaces and recharging station |
|
Credit Description |
Credit Reference |
Document Description |
|
|
|
For Developed Sites: Area of the site that is restored along with the landscape plan |
|
Credit Description |
Credit Reference |
Document Description |
|
|
|
Site photographs of structural and non-structural best management practices followed |
|
Credit Description |
Credit Reference |
Document Description |
|
|
|
Material data sheets of the products / materials conforming the SRI values |
|
Credit Description |
Credit Reference |
Document Description |
|
|
|
Calculation showing the water usage for base line case (both flow & flush fixtures) |
|
Credit Description |
Credit Reference |
Document Description |
|
|
|
Calculated design case water usage for sewage conveyance |
|
Credit Description |
Credit Reference |
Document Description |
|
|
|
Evidence for verifying the performance of installation of the systems to be commissioned. |
|
Credit Description |
Credit Reference |
Document Description |
|
Fundamental Refrigerant management |
|
Narrative |
|
Credit Description |
Credit Reference |
Document Description |
|
|
|
Plan and checklists for the follow-up review |
|
Credit Description |
Credit Reference |
Document Description |
|
|
|
Narrative of the waste recycling program (operative phase) by the client |
|
Credit Description |
Credit Reference |
Document Description |
|
|
|
Construction Waste Management Plan (CWMP) training photos and attendance sheets where applicable and relevant |
|
Credit Description |
Credit Reference |
Document Description |
|
Extracted, Processed & manufactured regionally |
|
Complete regional material calculation table including manufacturer, total product cost, percentage of product by weight that meets both extraction and manufacture criteria, distance from extractions/harvest/recovery site and project site; distance between manufacturing location and project site. Final Summary |
|
Credit Description |
Credit Reference |
Document Description |
|
INDOOR ENVIRONMENTAL CONTROL |
| |
|
Credit Description |
Credit Reference |
Document Description |
|
Outdoor Air delivery monitoring |
|
Narrative of the ventilation system |
|
Credit Description |
Credit Reference |
Document Description |
|
- Before Occupancy |
|
Site photographs of flushing |
|
Credit Description |
Credit Reference |
Document Description |
|
Indoor Chemical & Pollutant source control |
|
List of MERV 13 filters used in various equipments of the project |