Trakhees Guidelines GB 2.0 on General Deliverables of Green Building Commissioning Specialists

Status

In force

Issuing Authority

Ports, Customs and Free Zone Corporation

GOVERNMENT OF DUBAI
Ports, Customs and Free Zone Corporation

PCFC-Entity (Business Unit) Name : Trakhees (Dept. of Planning & Development)

Department Name: Civil Engineering Department (CED)

Section Name: Permits (Sustainability)

Document Reference Number: PCFC-TRK-CED-GB-G02

Revision Number: 02

Revision Date: December 2018

Classification: Public

 

Commissioning: 

Commissioning creates an Owner-Advocate quality review entity whose goals are to verify that the facility systems meet the functional and operational needs of the building's Owners and occupants. In plain language: to make very clear what the Owner's needs and wants are, and verify that these come to pass. It is an excellent way for an Owner to increase their confidence level during the period between conceptual planning and final construction.

 

The Commissioning Agent, also referred to as commissioning specialist or commissioning authority maintains a clear line of sight from project beginning to end, maintaining focus on the measurable Project Intent items, providing early detection and Owner counsel if the project begins to veer off course. Commissioning can be applied to any building component or manufacturing process, but is usually applied to Mechanical and Electrical (most commonly HVAC and control) building systems since these are the "moving parts - maintenance" systems and have historically been the most problematic.

 

A cornerstone of Commissioning work is early detection since the steps used in each phase of a design and construction project build upon each other. The sooner a correction is made in the sequence of events, the better for all parties involved since it avoids delays and re-work. Sampling techniques are used to spot check work processes along the way, smoothing out many of the bumps in the road. Special attention is given to correct issues that may otherwise 'build-in" problems to the building or its operations. Commissioning isn't rocket science - it uses experience, diligence, common sense, and empathy.

 

By considering the points of view and needs of each party in the design and construction team, coordination is greatly improved. Introducing the specialist to the design process helps assure the design team remains focused on the original project goals as they delve into all the details. Introducing the commissioning specialist to the construction process usually reduces RFI's and change orders, which benefits everyone involved and reduces schedule impacts. To achieve sustained benefits, the specialist maintains a focus on service access, clear and accurate documentation, and ample user training.

 

Commissioning Authority / Specialist
Scope of Services:

The commissioning specialist carries out several tasks at various phases of the project that can be outlined as under:

 

Commissioning Plan Development

1. The specialist will conduct a scoping meeting where the commissioning process is reviewed with the commissioning team members. The plan must contain the following elements:

a. Project Description.

b. Commissioning Overview.

c. Commissioned Systems List & Level of Rigor for Each System.

d. Design & Construction Stakeholders Data & Organizational Responsibility Matrix.

e. Identification of Stakeholders: Architect/Engineer, Owner's O&M Staff, Owner's Project Managers, Construction Managers and the Commissioning Agent.

f. Specific Responsibilities of each Stakeholder.

g. Definition of the commissioning roles and lines of communications for each member of the project team.

h. Definition of the commissioning process scope, in accordance with Green Building Regulatory Requirements / project needs.

i. Scope to include Pre-functional Checklists, Functional Testing Requirements, Final Documentation Checklists and Owner Training.

j. Verification.

k. Meetings & Communications Protocols.

l. Time Schedule of O&M Manuals, Training & Warrantees.

m. Appendix - Including any Abbreviations or Definitions.

 

Prior to Construction

1. Review and assist the Owner/developer in completing the scope of Commissioning services.

 

2. The commissioning specialist will work with the Architectural and Engineering team to develop a design intent document.

 

3. The commissioning specialist will perform a focused review of design documents at Schematic Design, Design Development, 50% CDs, 90% CDs and Final Contract Documents.

 

4. The commissioning specialist will finalize a Commissioning Plan as noted above in accordance with Green Building Regulatory Requirements/project needs.

 

5. The commissioning specialist will develop a commissioning specification with the design team that includes, but is not limited to:

a. Sample Pre-functional checklists and acceptance criteria for systems to be commissioned.

b. Sample Functional test procedures and acceptance criteria for systems to be commissioned.

c. Training planning and documentation requirements.

d. O&M Manual requirements and submission process.

 

6. Assist design team in completing commissioning specifications to be included in the construction documents.

 

7. The commissioning specialist will work with the designers to coordinate the general/technical specifications with commissioning specification.

 

8. The commissioning specialist will attend/participate in sustainable workshops as required during design.

 

9. Develop a preliminary Commissioning Plan using the current construction documents and the Basis of design document issued by the design team. Commissioning plan will be developed using an existing plan as a template.

 

10. Coordinate a controls integration meeting where the electrical and mechanical engineers and the commissioning specialist would discuss integration issues between equipment, systems and disciplines to ensure that integration issues and responsibilities are clearly described in the specifications.

 

11. The commissioning specialist will review training requirements of O&M staff and outline a training plan.

 

During Construction

1. Coordinate and direct the commissioning activities in a logical, sequential and efficient manner using consistent protocols and forms, centralized documentation, clear and regular communications and consultations- with all necessary parties, frequently updated timelines and schedules and technical expertise.

 

2. Coordinate the commissioning work and, with the contractor and Owner/developer, ensure that commissioning activities are being scheduled into the Contractor's Master schedule.

 

3. Plan, conduct, and attend commissioning meetings as needed. Maintain and distribute minutes.

 

4. Request and review additional information required to perform commissioning tasks, including O&M materials, contractor start-up and checkout procedures. Before start-up, gather and review the current control sequences and interlocks and work with contractors and design engineers until sufficient clarity has been obtained, in writing, to be able to write detailed testing procedures.

 

5. Review and approve normal Contractor submittals applicable to systems being commissioned for compliance with commissioning needs, concurrent with the Design Professional reviews.

 

6. Review requests for information and change orders for impact on commissioning and Design Team's Basis of Design Document.

 

7. Review coordination drawings to ensure that trades are coordinating work in a reasonable and logical manner.

 

8. With necessary assistance and review from installing contractors, write the functional performance test (FPT) procedures for equipment and systems. This will include manual functional testing, energy management control system trending and may include stand-alone data-logger monitoring. Submit to Owner/developer for review and approval.

 

9. Revise, as necessary, the construction phase commissioning plan developed during design, including scope and schedule, based upon approved submittals, RFI responses, Clarifications etc. that impact any aspect of the plan.

 

10. Review Commissioning plan with Owner/developer to confirm that the plan is acceptable to the Owner/developer.

 

11. Write and distribute construction checklists for commissioned equipment.

 

12. Develop an enhanced start-up and initial systems checkout plan with contractors for selected equipment.

 

13. Perform site visits, as necessary, to observe component and system installations. Attend selected planning and job-site meetings to obtain information on construction progress. Review construction meeting minutes for revisions/substitutions relating to the commissioning process. Assist in resolving any discrepancies.

 

14. Witness (spot check) HVAC piping pressure test and flushing, sufficient to be confident that proper procedures were followed. Include testing documentation in the Commissioning Record.

 

15. Witness (spot check) ductwork testing sufficient to be confident that proper procedures were followed. Include documentation in the Commissioning Record.

 

16. Document construction checklist completion by reviewing completed construction checklists and by selected site observation.

 

17. Document systems startup by reviewing start-up reports and by selected site observation.

 

18. Approve air and water systems balancing by spot testing and by reviewing completed reports and by selected...