Trakhees Green Building Regulation GB - 6.0 Warehouses & Industrial development

Status

In force

Issuing Authority

Ports, Customs and Free Zone Corporation

GOVERNMENT OF DUBAI
Ports, Customs and Free Zone Corporation

For projects with building permit obtained prior to DBC implementation

 

 

PCFC-Entity (Business Unit) Name

 

Department Name

 

Section Name

 

Document Reference Number

 

Revision Number

 

Revision Date

 

Classification

:

 

:

 

:

 

:

 

:

 

:

 

:

Trakhees - Ports, Customs & Free Zone Corporation

 

Civil Engineering Department (CED)

 

Permit Section (Green Buildings/Sustainability)

 

PCFC-TRK-CED-GB-REG-06

 

04

 

August 2016

 

Public

 

 

Item

DESCRIPTION

TYPE

AIM / INTENT

REQUIREMENT / CRITERIA

COMPLIANCE REQUIREMENTS

EVIDENCE REQUIRED AT DESIGN STAGE

NOC-BP

EVIDENCE REQUIRED AT POST-CONSTRUCTION STAGE NOC-BCC

A: GENERAL REQUIREMENTS 

 

 

ANNEXURE

Table No. 1 - Building Envelope

 

Building Element

Parameter

Requirements

Warehouse Structure (NON Conditioned Space)

 

Notes:

a. The values indicated above are applicable to the full development comprising warehouse, offices and associated areas.

b. Compliance to the above should be demonstrated by submitting relevant sections with Calculations.

 

Table No. 2 - Air Tightness / Envelope Tightness Guidelines

 

INFRARED THERMOGRAPHY

Eligibility Requirements of Thermographers

1. The thermographer should be suitably qualified/trained/certified - Level 1.

2. Affiliated to ATTMA/BINDT.

3. Minimum 2 years of demonstrable experience.

4. The testing technician should be competent enough to do the test according to the proper procedure and should be able to locate any leakages as well.

5. The technician should be equipped with sensitive and calibrated equipment to test the building according to the procedure.

 

CV should be submitted to Trakhees-CED (Green Building section) for review and approval.

 

Test Conditions 

The conditions (measurement circumstances) should follow the protocol of the referenced standard and should further ensure the following requirements are fulfilled.

 

1. Atmospheric circumstances and the temperature difference.

2. Wind speed and direction relative to the building.

3. An evenly distributed pressure across the area.

 

Reporting

The report should be comprehensive and of good quality that helps the professionals to make use of the information for proper corrective measures. It should follow the protocols of the standards and as a minimum comprise the following:

1. Background to the objective and principles of the test.

2. Location, orientation, date and time of survey.

3. Brief description of the construction of the building based on drawings or other available documentation.

4. Type(s) of surface material(s) used in the structure and the estimated value(s) of emissivity of this (these) materials(s).

5. A unique identifying reference.

6. Thermographer’s name, affiliation and qualifications.

7. Type of construction.

8. Weather conditions, wind speed and direction, last precipitation, sunshine, degree of cloud cover.

9. Ambient temperatures inside and outside before, at the beginning of the survey and the time of each image. Air temperature and radiant temperature should be recorded.

10. Inside air temperature and air temperature difference across the envelope during the examination.

11. Inside Relative Humidity data and outside Relative Humidity data for the duration of the test.

12. Precipitation, direction of the wind, and velocity of the wind during the examination.

13. Statement of any deviation from relevant test requirements.

14. Sketches and/or photographs of the building showing the positions of the thermographs.

15. Specification of the equipment used, including make, model and serial number , last calibration date, any known defects.

16. Thermographs indicating temperature levels obtained from the test, showing parts of the building where thermal anomalies have been detected, with indications of their respective positions, and the position of the IR camera with respect to the measurement target, and with comments on the appearance of the thermal images, if possible with reference to parts of the building envelope with acceptable performance.

17. Date and signature and professional seal.

18. Type, extent and position of each observed defect.

19. Results of any supplementary measurements and investigations.

 

 

BLOWER DOOR TESTING

Eligibility Requirements of testing company

1. A blower door testing training certificate provided by an ATTMA/BINDT Certified testing organization of suitable Level required for undertaking the tests.

2. Minimum 2 years of demonstrable experience.

The testing technician should be competent enough to do the test according to the proper procedure and should be able to locate any leakages as well. CV should be submitted to Trakhees for review and approval.

3. The technician should be equipped with sensitive and calibrated equipment to test the building according to the procedure.

 

Test Conditions

1. The ambient atmospheric conditions (measurement circumstances) should be measured before and after the tests and should follow the CIBSE TM23 - “Testing of buildings for air leakage" protocol and the referenced standard. Measurements taken for following are to be within acceptable limits as described in the CIBSE TM23 guidelines:

a. Temperature.

b. Humidity.

c. Wind speed.

d. Barometric pressure.

 

2. 2 Bias pressure readings to be taken before and after test and averaged as described in the CIBSE TM23 guidelines.

 

Reporting

The report should be comprehensive and of good quality that helps the professionals to make use of the information for proper corrective measures. It should follow the protocols of the standards and as a minimum comprise the following:

1. Background to the objective and principles of the test.

2. Location, orientation, date and time of the test.

3. Brief description of the construction of the building based on drawings or other available documentation.

4. Description of the activities, measurement conditions and if applicable any notes about closed or opened doors etc.

5. Presentation of the measurement-results as well as any digital (visual) images of the object.

6. In case the building doesn’t pass the test: evidence of leakage provided with the use of visual or thermal images.

7. Conclusions and recommendations.

 

Table No. 3 - Minimum HVAC system performance criteria (EER)

SPLIT AND PACKAGED UNITS

 

S. No.

Capacities

EER (Minimum)

1.

Less than 2.5TR

11.8

 

CASSETTE TYPE UNITS EER ≥ 11.5

 

Notes: 

1. The above table stipulates the minimum HVAC energy efficiency requirement (system performance and has taken into consideration the minimum requirements of ASHRAE 90.1 stipulated vide its Table 6.8.1A and the high energy optimization needs of the jurisdiction. This also reiterates that under no circumstances would the EER be less that the ASHRAE stipulated values.

 

2. It is a well-known fact that HVAC systems consume up to 75% of the building energy consumption especially during summer. These basic EER requirements in conjunction with integrated design principles and other adequate green measures taken during design and construction stages of the project would greatly enhance the operational sustainability of the facility through efficient performance of the HVAC systems.

 

Table No. 4 - Recommended Light Power Densities

Internal Lighting

 

S. No.

Area / Zone

Light Power Density(LPD)

Watt / Ft2

1.

Open Offices

0.8

 

External Lighting

 

Synod

Area / Zone

Light Power Density(LPD)

Watt / Ft2

1.

Canopies and overhangs

0.5

 

Notes:

a. The light power densities indicated above are improvements over those levels mentioned in ASHRAE 90.1-2007.

b. Submissions should comprise LPD tables for the project comprising the proposed values in relation to Trakhees specified values for different areas.

 

Table No. 5 - Minimum performance criteria for sanitary wares

 

Fixture Type

Requirements

REMARKS

Water Closets

3/6 l/flush

Dual flush type

 

Notes:

1. The table provides an outline/guidance on the flow and flush fixture requirements to be used in the project. This however does not stop a project from seeking higher efficiencies.

 

2. It should be ensured that laundry equipment , dish washers etc. that have not been mentioned in the above table are selected from energy star/equivalent accredited products for achieving maximum water savings.

 

Table No. 6 - VOC Limits

PAINTS:

Interior Coatings:

 

Coating Type

VOC weight in grams/liter of product minus water

Non-flat

150

 

Exterior Coatings:

 

Coating Type

VOC weight in grams/liter of product minus water

Non-flat

200

 

ANTI-CORROSIVE PAINTS:

 

Coating Type

VOC weight in grams/liter of product minus water

Gloss

250

 

CLEAR WOOD FINISHES:

 

Coating Type

VOC weight in grams/liter of product minus water

Varnish

350

 

FLOOR COATINGS: 100g/l 

 

SEALERS:

 

Coating Type

VOC weight in grams/liter of product minus water

Waterproofing sealers

250

 

SHELLAC:

 

Coating Type

VOC weight in grams/liter of product minus water

Clear

730

 

STAINS: 250g/l

 

Architectural Applications

VOC Limit (g/L less water)

Specialty Applications

VOC Limit (g/L less water)

indoor carpet adhesives

50

PvC welding

510

 

NOTES:

a. The above tables provide prescriptive criteria through which a development is expected to comply with the minimum requirements specified therein.

b. While the table indicates the minimum level, it does not discourage/restrict the stakeholder in seeking higher levels of performance.

c. It is strongly suggested the consultants undertake building energy simulation to demonstrate improvement in building performance by optimizing various factors.

d. It is inherent that significant importance is to be attached to the performance of the villas based on the actual utility and requirement which exceeds the basic requirement set by the prescriptive approach.