TO: All Business Units Of Dubai World, Their Clients, Green Building Consultants, Architectural & Engineering consultants, Contractors and relevant stakeholders
SUBJECT: Green Building Compliance - Post NOC-Building Permits (BP)
DATE: 1 January 2016
We would like to begin by wishing all of you a very happy 2016!!
This circular is being initiated on the back of our observations on actual site level implementation of green building regulations after they are awarded with NOC-BP and accordingly attempts to put forward corrective mechanisms for better compliance. Our observations and proposed suggestions are tabulated below for your attention:
| No | Subject | Observation/Corrective Action |
| 1 |
Communication with GB Consultants
(Applicable to projects that have appointed Green Building consultants)
(Warehouse/Villa Projects) |
We note that the consultants and contractors are not updating the GB consultants on the approvals. This prevents the green building consultants from actively contributing to the project i.e. Green briefing, Inspections, site level compliance etc.
Please... |