Trakhees Circular No.CEDGR-50 of 2017 Improvement of the Building Permit/NOC Process (Updated)

Status

In force

Issuing Authority

Ports, Customs and Free Zone Corporation

Effective date

XX.XX.XXXX

Official Link

https://

To: All Business Units/Clients / Consultants

Date: 22 June 2017

Our Ref: CEDGR-50

Subject: Improvement of the Building Permit/NOC Process (Updated)

 

Trakhees Civil Engineering Division is pleased to amend the circular ref. Circular-102936/2012/MAS issued in 30th October 2012 for better flexibility when the contractor documents are not available during the time of submission as follows:-

- The consultant can submit for Building Permit/NOC services. Trakhees will carry out the required technical review and approval notification of 6 months validity will be issued.

- Within the validity period, the contractor shall be appointed and the consultant shall apply to collect the Building Permit/NOC.

- Additional 6 months could be granted to collect the Building Permit/NOC subject to providing an accepted justification and revalidation fee will be applied. No further extension will be accepted and therefore new submission for BP/NOC shall be applied as per common procedures.

 

Thank you in advance for your compliance and cooperation.

 

 

Eng. Abdulla Belhoul

Director - Trakhees Civil Engineering ...