RAR/VER1/04-20
(1) Part 5A of the Regulatory Law (the Law) and this Module (RAR) apply to an Authorised Firm that is authorised under its Licence to carry on any one or more of the following Financial Services:
(a) Accepting Deposits;
(b) Providing Credit,
(c) Dealing in Investments as Principal; or
(d) Managing a Profit-Sharing Investment Account where that account is received on an unrestricted basis (a PSIAu).
(2) Where specified these Rules also apply to a Parent or Subsidiary of the Authorised Firm or to another entity in its Group.
Guidance
Rule 1.2.1 sets out are a number of mainly technical definitions used only in RAR. The definitions do not also appear in GLO unless they are used elsewhere in the Rulebook. GLO also contains definitions used in RAR. In some cases, GLO definitions are replicated in Rule 1.2.1 for convenience where those definitions are embedded in RAR specific definitions. Commonly used definitions such as “Authorised Firm”, “Financial Service” and “Group” appear only in GLO.
In this module, the terms and abbreviations listed in the table below have the following meanings:
| AT1 Capital | Has the meaning given in PIB Rule 1.2.1. |
| Bail-In Tool | The Resolution Tool referred to in Articles 84N(1)(i) and 84P of the Law. |
| Critical Functions |
Activities, services or operations the discontinuance of which is likely to lead to: (a) the disruption of services that are essential to the financial services industry in the DIFC or to the UAE economy; or (b) the disruption of financial stability due to the size, market share, external or internal interconnectedness, complexity, or cross border activities of an Authorised Person or its Group, with particular regard to the substitutability of those activities, services or operations. |
| Debt Instrument | Bonds and other forms of transferable debt, instruments creating or acknowledging debt and an instrument giving rights to acquire such instruments. |
| Pre-Resolution Valuation | A valuation referred to in Article 84M(1) of the Law. |
| Provisional Valuation | A valuation referred to in Article 84M(2) of the Law. |
Guidance
In accordance with Article 84D of the Law, an Authorised Firm is required to prepare and submit a Recovery Plan to the DFSA if it is included in a class of Authorised Firms required to prepare and submit such a plan or if it is not included in such a class but has been given written notice by the DFSA that it has to prepare a plan. Rule 2.1.1 prescribes the class of Authorised Firms require to prepare and submit a Recovery Plan.
An Authorised Firm shall prepare and submit to the DFSA for review a Recovery Plan if it is authorised under its Licence to carry on either or both of the following Financial Services:
(a) Accepting Deposits; or
(b) Managing a Profit-Sharing Investment Account where that account is received on an unrestricted basis (a PSIAu).
(1) The Recovery Plan for an Authorised Firm referred to in Rule 2.1.1 shall be submitted to the DFSA:
(a) in the case of an Authorised Firm that has an authorisation referred to in that Rule on the commencement day, no later than two months from the commencement day; or
(b) in the case of an Authorised Firm that receives such an authorisation after the commencement day, no later than two months from the date on which the authorisation is granted.
(2) Where the DFSA gives an Authorised Firm written notice under Article 84D(1)(b) of the Law that it must prepare a plan, the Authorised Firm shall submit the Recovery Plan to the DFSA by no later than the date specified in the notice.
(3) Where the DFSA gives an Authorised Firm written notice under Article 84D(5) of the Law requiring it to take measures to rectify any deficiencies in the Recovery Plan, the Authorised Firm shall submit the rectified Recovery Plan by no later than the date specified in the notice.
2.1.3
An Authorised Firm shall ensure that the Recovery Plan processes and implementation are integrated, and aligned, with its overall governance structure, processes and internal risk management frameworks, such as its early warning indicators.
2.1.4
(1) An Authorised Firm shall ensure that it has in place appropriate contingency arrangements, which will enable it to continue to operate if it implements Recovery Measures set out in the Recovery Plan.
(2) The contingency arrangements under (1) shall include processes relating to IT, access to financial market infrastructure such as clearing and settlement facilities, and the continuation of supplier and employee contracts.
(1) An Authorised Firm shall designate a Senior Manager who will be responsible for leading, formulating and overseeing the Recovery Planning process, including providing to the DFSA any information relevant for the review of the Recovery Plan.
(2) The Authorised Firm shall notify the DFSA of the Senior Manager designated under (1).
(3) Without limiting the generality of the Principles for Authorised Individuals in GEN Rule 4.4, the senior management of an Authorised Firm are responsible for the Recovery Planning of that Authorised Firm.
A Recovery Plan prepared by an Authorised Firm shall be prepared on the following basis:
(a) if the Authorised Firm has its head office in the DIFC, the Recovery Plan shall cover the recovery of the entire Group;
(b) if the Authorised Firm is a Subsidiary of a Financial Institution that has its head office outside the DIFC, the Recovery Plan shall specifically address stress scenarios and triggers for the Authorised Firm and adequately cover any downstream operations, as well as including specific recovery options for the DIFC operations; and
(c) if the Authorised Firm is a Branch of a Regulated Financial Institution, the Recovery Plan may generally be part of the Group plan, provided the Recovery Plan adequately covers the DIFC operations.
Guidance
1. For a Branch with significant DIFC operations, the Recovery Plan should be tailored to the local operations and contain all relevant information. For a Branch with limited operations, the DFSA may accept considerable reliance on a Group plan, provided the Branch can demonstrate how the Recovery Plan options can be effectively applied to address stress events that pose a risk to the Branch’s viability.
2. The DFSA will approach the Recovery Plan requirements in a proportionate manner.
A Recovery Plan shall be commensurate with the nature, complexity, interconnectedness, size and substitutability of the Authorised Firm’s DIFC operations, and set out the Recovery Measures the Authorised Firm can take, as well as how and when it can take them, including the following key elements:
(a) consideration of a range of scenarios including both idiosyncratic (specific to the Group or Authorised Firm) and market-wide scenarios, likely to cause severe stress which will require Recovery Measures to be considered or activated;
(b) the actual Recovery Measures, which may include measures to reduce the Authorised Firm’s risk profile, address capital shortfalls or liquidity pressures, change funding strategy, or change governance structure; and
(c) processes to ensure the timely implementation of Recovery Measures in a range of stress situations.
(1) A Recovery Plan shall include:
(a) a summary of the key elements of the plan and a summary of overall recovery capacity;
(b) a summary of the material changes to the Authorised Firm since the most recently filed Recovery Plan;
(c) a communication and disclosure plan outlining how the Authorised Firm intends to manage any potentially negative market reactions;
(d) a range of capital and liquidity actions required to maintain or restore the viability and financial position of the Authorised Firm;
(e) a framework of indicators which identify the points at which appropriate actions referred to in the Recovery Plan may be taken;
(f) an estimate of the timeframe for executing each material aspect of the Recovery Plan;
(g) a detailed description of any material impediment to the effective and timely execution of the Recovery Plan, including consideration of impact on the rest of the Group, customers and counterparties;
(h) identification of Critical Functions;
(i) a detailed description of the processes for determining the value and marketability of the Core Business Lines, operations and assets of the Authorised Firm;
(j) a detailed description of how recovery planning is integrated into the corporate governance structure of the Authorised Firm as well as the policies and procedures governing the approval of the Recovery Plan and identification of the persons in the organisation responsible for preparing and implementing the Recovery Plan;
(k) arrangements and measures to conserve or restore the Authorised Firm’s own funds;
(l) arrangements and measures to ensure that the Authorised Firm has adequate access to contingency funding sources, including potential liquidity sources, an assessment of available collateral and an assessment of the possibility to transfer liquidity across Group entities and business lines, to ensure that it can continue to carry out its operations and meet its obligations as they fall due;
(m) arrangements and measures to reduce risk and leverage;
(n) arrangements and measures to restructure liabilities;
(o) arrangements and measures to restructure business lines;
(p) arrangements and measures necessary to maintain continuous access to financial markets infrastructures;
(q) arrangements and measures necessary to maintain the continuous functioning of the Authorised Firm’s operational processes, including infrastructure and IT services;
(r) preparatory arrangements to facilitate the sale of assets or business lines in a timeframe appropriate for the restoration of financial soundness;
(s) other management actions or strategies to restore financial soundness and the anticipated financial effect of those actions or strategies;
(t) preparatory measures that the Authorised Firm has taken or plans to take in order to facilitate the implementation of the Recovery Plan, including those necessary to enable the timely recapitalisation of the Authorised Firm; and
(u) stress scenarios that consider the Financial Stability Board (FSB) “Guidance on Recovery Triggers and Stress Scenarios”, relating them to the Authorised Firm’s particular business model and specific fragile points which can cause it to become non-viable or fail.
(2) The Recovery Plan of a DIFC Company, or a Branch of an international Group, shall include at least two scenarios:
(a) one DIFC entity-specific scenario; and
(b) one macroeconomic scenario that impacts the DIFC entity,
and the scenarios are to be tested to ensure that the Recovery Plan is suitable for use in a range of various types of stress.
Guidance
1. The Recovery Plan should serve as a guide or a “road map” for the Authorised Firm and the DFSA in a recovery scenario, i.e., a situation of distress where there is still a reasonable prospect of recovery, if appropriate Recovery Measures are taken, and the Resolution Conditions have not been met.
2. While the stress scenarios in Recovery Plans need not be the same for all Authorised Firms, they should be realistic and specific to each Authorised Firm’s business model. The DFSA will check the assumptions used in the scenarios and may require additional scenarios.
3. The DFSA expects a Recovery Plan to adopt a structure, as follows:
a. a high-level substantive summary of the key recovery strategies;
b. the analysis that underlies the key recovery strategies;
c. a range of factors indicating that the implementation of Recovery Measures may be necessary (recovery indicators);
d. tangible and practical options for Recovery Measures;
e. description of preparatory actions to ensure that the Recovery Measures can be implemented effectively and in a timely manner;
f. an operational plan for implementation of the Recovery Plan, including sequencing and indication of time needed for implementing each step;
g. details of any potential material impediments to an effective and timely execution of the Recovery Plan and how these are being addressed;
h. responsibilities for executing the preparatory actions, triggering the implementation of the Recovery Plan and the actual Recovery Measures; and
i. internal and external communication and disclosure plan to manage any potential negative market reactions, if applicable.
4. The strategic analysis referred to in item 3.b should include the Authorised Firm’s analysis and, where relevant, identification of essential and systemically important functions carried out by the Authorised Firm, which it should aim to maintain as part of the recovery process. The strategic analysis should also cover:
a. actions necessary for maintaining operations of, and funding for, those essential and systemically important functions, if such are identified;
b. assessment of the viability of any business lines and legal entities which may be subject to separation (sale) in a recovery scenario, as well as the impact of such separation on the remaining Group structure;
c. assessment of the likely effectiveness of each material aspect of the Recovery Measures and potential risks related thereto, including potential impact on customers, counterparties and market confidence;
d. underlying assumptions for the preparation of the Recovery Plan; and
e. processes for determining the value and marketability of the material business lines, operations, and assets.
5. The recovery indicators referred to in item 3.c. are both quantitative and qualitative metrics that identify points at which an Authorised Firm has to decide whether an action referred to in its Recovery Plan should be taken. The types and number of indicators should be appropriately selected to be well-targeted, but not to render the exercise unmanageable. They should be calibrated, and not linked to inherently lagging metrics, and to ensure sufficient notice to decide on the corrective action for the DFSA, so as to begin contingency planning.
6. A number of quantitative recovery indicators should, as a minimum, be included:
a. Capital (e.g. CET1, total capital and leverage ratio);
b. Liquidity (e.g., LCR or NSFR (as defined in PIB), cost of wholesale funding, deposit withdrawal, increased collateral demands);
c. Profitability (e.g. return on equity (RoE) or return on assets (RoA), significant operational losses);
d. Asset quality (e.g. non-performing loan (NPL) rate, including off-balance sheet (OBS)); and
e. Market aspects (e.g. rating downgrades, negative review, credit default swap (CDS) spreads).
7. The qualitative recovery indicators could include, for example, difficulties in issuing liabilities at current market rates, an unexpected loss of senior management, adverse court rulings, negative market press and significant reputational damage to franchise.
8. The recovery indicators should be closely connected with the Authorised Firm’s early warning indicators, which should form part of its internal risk management. They should be designed to prevent undue delays in the eventual implementation of Recovery Measures.
9. The expected result of one of several indicators occurring should lead to an appropriate, and clearly described in the Recovery Plan, internal escalation procedure to the senior management and the Board, without, however, leading to an automatic activation of the Recovery Plan.
10. The Recovery Measures can include a host of actions to be taken by the Authorised Firm alone or in combination, depending on the circumstances and the business model of the Firm. The Authorised Firm should consider each situation on a case-by-case basis.
11. The Recovery Measures may include, among other things:
a. actions to strengthen the capital profile through capital raising or capital conservation measures such as suspension of dividends and payments of variable remuneration;
b. restructuring business lines with a view to permitting carrying out of sales of downstream entities and spin-off of business units, sales of assets or loan portfolios;
c. voluntary restructuring of liabilities (e.g. through debt-to-equity conversion);
d. liquidity improvement options through, for example, securing funding via various techniques such as improved valuation of available collateral, repurchase agreements (“repo”), bonds issuance, monetisation of unencumbered assets; and
e. reduction of RWA (as defined in PIB) or leverage.
12. In terms of contingency funding sources, while it is conceivable that parental financial support would, in many cases, be the most credible recovery option, Authorised Firms are expected to consider all funding options available, at the level of the DIFC entity, and set them out in the Recovery Plan.
Guidance
1. The DFSA may, where it considers it necessary and practicable to do so, prepare a Resolution Plan for an Authorised Firm (see Article 84E of the Law).
2. The DFSA may, in preparing a Resolution Plan:
a. create the Resolution Plan, or parts thereof, itself;
b. amend or accept a resolution plan, or parts thereof, created or provided by the Authorised Firm or any other person (such as a Resolution Authority in another jurisdiction); or
c. prepare the Resolution Plan using a combination of a. and b.
3 Where it has prepared a Resolution Plan, the DFSA may review and update it:
a. on a regular basis; or
b. after material changes to the legal or organisational structure of the Authorised Firm, or to its business or financial position, which could have a material effect on the effectiveness of the Resolution Plan.
4. The Resolution Plan may set out any relevant matters, including the following:
a. financial and economic functions for which continuity is critical;
b. the resolution strategy and the Resolution Powers or Resolution Tools which the DFSA would plan to take if the Authorised Firm concerned met the Resolution Conditions, particularly in view of preserving Critical Functions;
c. options for exercising Resolution Powers and applying Resolution Tools in the context of the potential Resolution scenarios;
d. data requirements for the Authorised Firm’s operations, structures and Critical Functions;
e. potential barriers to effective Resolution and actions to mitigate these;
f. actions to protect depositors and for the prompt return of Client...