Unified UAE Legislation Database
Machine-read text — original PDF attached

Ras al-Khaimah Executive Council Decision No. 7 of 2025 Regarding the adoption of the registers of fees and penalties under the Ras al-Khaimah Law No. 12 of 2021 Regarding the regulation of demolition and clearance works in the Emirate of Ras al-Khaimah

Status

In force

Issuing Authority

Ras Al Khaimah Executive Council

We, Mohammed bin Saud bin Saqr Al Qasimi, Crown Prince of Ras Al Khaimah and the Chair of the Executive Council

Having regard to the Ras Al Khaimah Municipal Law of 1981 and its amendments. and Law No. (7) of 2012 concerning the establishment of the Executive Council of the Emirate of Ras al-Khaimah.

And Law No. (12) of 2021 on the regulation of demolition and clearance works in the Emirate of Ras al-Khaimah and its Executive regulation.

Following approval by the Executive Council.

We have therefore issued the following decision:

Article (1)

The following words and phrases shall have the meanings set out opposite each one, unless the context otherwise requires:

Ras Al Khaimah Municipal Department:The Department
The Department’s Buildings Management Division:Management
Article (2)

The fees set out in the Register attached to this Decision shall be levied. These fees are payable in return for the services specified opposite each entry.

Article (3)

Without prejudice to any more severe penalty provided for in the laws in force. Any person who commits any of the offences set out in the Register attached to this Decision shall be liable to the fine and measures specified in respect of each offence. The fine shall be doubled in the event of a repeat offence within one year of the date on which the previous offence was committed.

Article (4)

Any interested party may lodge an appeal with the Administration against any infringements, fines or measures taken against them pursuant to the provisions of this Decision. Such an appeal must be lodged within thirty days of the date on which the party was notified of the fine or measure being appealed against. The Technical Committee for Demolition and Clearance, or any of the Grievances Committees designated by the Director-General, shall adjudicate on such an appeal within thirty days of the date on which it is lodged. The Decision issued in respect of the appeal shall be final.

Article (5)

The Department may offer consideration to the offender in return for a sum not less than a quarter of the fine imposed for the offence. This is subject to the causes of the offence being rectified within the period specified by the Department.

Article (6)

All fees and fines shall be paid into the Department’s treasury. Should they remain unpaid, they shall be recovered by means of a claim issued by the Director General, specifying the name of the debtor and their legal representative, and the amount due. This claim shall constitute an enforceable instrument to be enforced by the competent enforcement judge in accordance with the provisions of the Code of Civil Procedure.

Article (7)

Any provision in any other Decision that is inconsistent with the provisions of this Decision shall be abrogated.

Article (8)

This decision shall come into force on the date of its issue and shall be published in the Official Gazette.

Mohammed bin Saud bin Saqr al-Qasimi Crown Prince of Ras al-Khaimah Chair of the Executive Council

Issued today, the 26th of Shawwal in the year 1446 AH Corresponding to the 24th of April 2025 AD

Schedule of Fees
DecreesService descriptionM
100 dirhamsApplication for a demolition and clearance licence1
100 dirhamsApplication for a Certificate of Completion of Demolition and Clearance Works2
Register of Offences
The measureFine
(The fine shall be doubled in the event of a repeat offence within one year of the date on which the previous offence was committed)
Description of the offenceM
Demolition and clearance work is to be suspended until a licence has been obtained, and the machinery and tools used in the offence are to be impounded40,000 dirhams for both the owner and the contractorDemolition or removal of a building without a licence1
Demolition and clearance work is to be suspended until the causes of the breach have been rectified20,000 dirhams each for the contractor and the consultantDemolition carried out in a manner that poses a risk to passers-by or neighbouring buildings2
7A temporary wall is being erected that does not comply with the requirements specified by the Department2,000 dirhamsDemolition and clearance work is to be suspended until the causes of the breach have been rectified
8Failure to display a sign containing the details of the Licence or the demolition and clearance Decision in accordance with the specifications set by the Department2,000 dirhamsA sign shall be erected at the offender’s expense should...