We, Mohammed bin Saud bin Saqr Al Qasimi Crown Prince of Ras Al Khaimah and the Chair of the Executive Council
Having examined Decree-Law No. 37 of 2021 concerning the Commercial Register.
and the Ras al-Khaimah Municipal Law of 1981, as amended.
and the Buildings Regulation Act No. (1) of 2009.
and Law No. (7) of 2012 concerning the establishment of the Executive Council of the Emirate of Ras al-Khaimah.
and Law No. (8) of 2016 on the regulation of economic activities in Ras al-Khaimah.
and Law No. (8) of 2019 on the regulation of the practice of the building contract profession, as amended.
and Law No. (10) of 2019 on the regulation of the practice of engineering consultancy, as amended.
and Law No. (11) of 2023 on the regulation of surveying activities in the Emirate of Ras al-Khaimah.
Following approval by the Executive Council.
We have issued the following regulations:
The following words and phrases shall have the meanings set out opposite each one, unless the context otherwise requires.
The Emirate : The Emirate of Ras al-Khaimah.
The Department : Ras Al Khaimah Municipal Department.
Director General: The director general of the Department. Competent Department: The Department’s Buildings Department. Relevant department: The Rehabilitation Department within the Competent Department. Committee: A committee responsible for examining matters and providing an opinion to the relevant part. Competent authority: The authority responsible for issuing commercial licences to construction companies in the emirate. Establishment: Any company or organisation with a licence to carry out construction work. The Register: An electronic register for the registration and classification of construction firms licensed to practise the construction trade in the emirate, as well as engineers accredited by the Department.
The following procedures shall be followed when registering engineers in the Register and classifying them into the appropriate category:
b. A copy of the academic qualification certificate, stating the grade achieved, the field of study, the date of graduation, the university and the State in which the qualification was obtained. c. The professional experience gained in his/her field of specialisation, the number of years of such experience, and the relevant training certificates and professional accreditations. (c) The engineer’s membership number and date of membership of the Emirates Society of Engineers. c. A statement listing the construction companies for which he has worked and the roles and responsibilities assigned to him at each. h. A certificate of good character. (d) Any other data specified by a Decision of the Committee. 2. Once the information and documents specified in Clause 1 of this Article have been provided: the Competent Department shall register the engineer in the Register and classify him or her in the appropriate category set out in Registers 4 and 5 annexed to these Regulations, provided that the following conditions are met: A. The applicant must hold a Bachelor’s degree in Engineering from a recognised university in the engineering discipline for which the Licence is sought. b. Be a member of the Emirates Society of Engineers. (t) Be of good character and conduct. (i) He must have a number of years’ experience qualifying him for the appropriate category, in accordance with Registers 4 and 5 attached to these Regulations. c. He must be residing at the premises for which registration is sought. If he is registered as part of the facility’s engineering staff, it is sufficient to submit a temporary work permit issued by the relevant authority. h. To pass the examination specified by the relevant Part for each category. (d) Any other conditions specified by a Decision of the relevant Part.
The following procedures shall be followed when registering and classifying construction enterprises in the Register:
the managing director, the company’s registered office, its location, its floor area and the scope of the construction activities for which it is licensed.
The Competent Department is responsible for the initial registration of the establishment in the Register.
Once all the information and documents specified in the first Clause of this Article have been submitted, the Committee shall issue an opinion to the relevant Part regarding the registration of the contracting enterprise and its classification into the category set out in Table No. (6) annexed to these Regulations, within thirty days of the date on which the information and criteria specified for classification have been met.
Following receipt of the committee’s opinion, the relevant part is responsible for approving the registration and issuing a certificate of registration for the establishment, setting out the establishment’s details and classification category.
In the event of a refusal to register and classify, the competent Part shall issue a reasoned Decision to that effect and notify the establishment thereof by one of the means set out in Article 18 of these Regulations.
The Director-General – on the recommendation of the Competent Department – may amend the criteria for classifying establishments or add new criteria, in particular those relating to the number of workers.
The Competent Department may – based on the opinion of the Part – authorise contracting firms to form a temporary consortium for the implementation of a specific project, in accordance with the conditions and regulations set out in a Decision issued by the Director-General; the consortium shall be classified within the category for which the necessary criteria are met, and the provisions applicable to that category shall apply to it.
The Competent Department must be notified of any change to the establishment’s Licence details or to the details of its technical staff within thirty days of the date of the change.
The Committee may, at any time, have the establishment removed from the Register if it fails to comply with, or ceases to meet, any of the conditions required for registration and classification.
Construction companies may apply for temporary work permits for workers in accordance with the percentage specified by the relevant part.
The data in the Register of construction enterprises must be updated on an ongoing basis, in particular the data relating to the share of allocated space for each enterprise, performance efficiency results, suspension cases, and details of penalties, and any other data specified by a Decision of the relevant Part.
The main contractor’s organisation must register the contract with the subcontractor with the Department in accordance with the procedures and conditions specified by the Department.
In addition to the classification criteria for construction projects set out in these regulations, a company or organisation must hold liquid financial assets sufficient to cover its liabilities should any of the conditions specified in a Decision issued by the Director-General be met, provided that these assets include the following:
Cash and bank deposits.
Property, equipment and vehicles.
Accounts receivable for which collection has been confirmed after the balance sheet date or for which the accuracy of the balances has been certified by government entities.
Businesses in progress where payment is received after the balance sheet date.
Expenses paid in advance or similar.
Any other assets approved by the Department.
The financial position of a contracting firm shall be audited by a certified auditor, or by any body designated by the Department, in accordance with the format and requirements specified by the Department.
Contractors specialising in the demolition of buildings and the clearance of rubble shall be registered and categorised in accordance with the same procedures set out in Article 4 of these Regulations, taking into account the technical and administrative criteria set out in Table No. (7) attached to these Regulations.
Contracting firms specialising in the construction of metal structures and the installation of precast concrete structures shall be registered and categorised in accordance with the same procedures set out in Article (4) of these Regulations, taking into account the technical and administrative criteria set out in Register No. (8) annexed to these Regulations.
Entities engaged in infrastructure contracting activities shall be registered and categorised in accordance with the procedures set out in Article 4 of these Regulations, taking into account the technical and administrative criteria set out in Table No. (9) annexed to these Regulations.
A contracting firm that is registered and categorised in the Register shall take one of the following forms:
It is the entity whose head office is established and its licence is issued in the emirate.
It is a section of an establishment classified in one of the emirates of the State. The following conditions must be met for its registration and classification:
A. The applicant must have practised the contracting profession in one of the areas of contracting activity set out in these regulations for a period of not less than three years in one of the Emirates of the State. b. It must have a team of specialist engineers for each area of contracting activity it intends to undertake. (t) That the Section be registered and classified in accordance with the procedures followed by the Department.
It is a Section of a foreign contracting firm established in the Emirate; the following conditions must be met for its registration and classification:
This is an entity established in the Emirate in accordance with the provisions of the Companies Law, as a joint venture between a local construction firm classified in Category 1 and a foreign contractor who does not have a section within the State. For its registration and classification, the foreign contractor must meet the following conditions:
Where an engineer or a construction firm submits an application to the relevant Part to amend their classification, the following procedures must be followed when considering the application:
The owner of the establishment shall be responsible for signing the contract with the project owner or their authorised representative. Without prejudice to the licence holder’s responsibility to the Department, the licence holder may appoint a manager for the establishment to whom the tasks of signing and acting on behalf of the establishment are delegated, provided that the manager meets the following conditions:
A works contract must include the following essential details and conditions:
The date of the contract, the parties to it, their addresses and their contact details.
A detailed description of the construction works covered by the contract and the contractor’s duties and obligations in relation to the project.
To specify the agreed timeframe for carrying out the business activities, the agreed fees and the manner in which they are to be paid.
To determine how business on the project is to be amended and the mechanism for doing so.
How late payment penalties are determined, the conditions governing them, and the mechanism for their enforcement.