Guide to Calculating Property Developers’ Percentages of Completion for Property Units

Status

In force

Issuing Authority

Dubai Land Department

Land Administration

Date of issue: 28 February 2022

Document details

AccreditationReviewPreparation 
His Excellency Sultan Butti bin MajranHis Excellency Marwan bin GhalitaMr Mohammed Khader Al-DahName
Director General of the Land DepartmentChief Executive of the Real Estate Regulatory AgencySenior Manager, Surveying Department, Register and Property Services SectorJob title

Releases

DateDocument titleEdition
17 July 2016Guidelines and Standards for Technical Reports on Project Monitoring1
1 October 2018
(Decision 191/2018)
A Guide to Calculating and Determining the Percentage of Completion for Property Development Projects2

Land Administration Reference:

Guide to Calculating the Percentage of Completion

Chapter 1: Introduction

This guide is the official document used to calculate the percentage of completion of projects and off-plan property units sold. The Department, through the Surveying Directorate, carries out site visits to monitor projects and calculate the percentage of completion in accordance with this guide.

Chapter 2: Definitions

For the purposes of this guide, the definitions of the most important terms are set out below:

DefinitionThe term
The Land Department in Dubai.The Department
Dubai Real Estate Regulatory Agency.The Foundation
Included in the development. The floor area is calculated in accordance with the approved International Property Measurement Standards via www.ipmsc.org 
It is the company or body responsible for the design, sale and construction of a property development in the emirate in accordance with the laws in force.The developer

Chapter 3: Objectives of the Guide

Among the objectives of the guide are:

  • Statement on the method for calculating the percentage of completion for projects shown on the map.
  • List of the types of technical reports issued by the Department.
  • Statement on the uses of technical reports.
  • A statement on the importance of defining and describing the project before commencing the sales process and construction work.
  • To ensure transparency for dilers in the property market and to raise their awareness.

Chapter 4: Key Responsibilities

The key responsibilities set out in this guide are as follows:

Duties and ResponsibilitiesThe official
Approval of the guide and any necessary revisions.Director-General
Approval of documents relating to organisational units within the sectorExecutive Directors

Title 5: Basis for Calculating the Percentage of Completion

For the purposes of this guide, the percentage of completion is calculated on the basis of the building areas that have been completed on site. Time, money or any other basis must not be used in calculating the percentage of completion. It is not permitted to calculate a future or estimated percentage for business that has not been completed by the date of the engineer’s site visit.

The formula for calculating the percentage of completion is:

$$C = B \times A$$

To elaborate:

C =B xA
Percentage of completion of specialist construction works.Weighting of specialist construction works in the project based on the cost of the specialist construction item. (Weighting)Percentage of completion of specialist construction works based on the area completed. (On-site progress)
  • An illustrative example in Title 11 of this guide, under the ‘Outputs’ clause.

Title 6: Quantifiable elements of the project

  1. Buildings (above ground), including detached and semi-detached villas, commercial and residential buildings, shopping centres, property units and any other type of building, as approved by the Real Estate Development Guarantee Accounts Department.
  2. Infrastructure.

Chapter 7: Types of Reports

This guide includes the following reports:

  1. Overall reports: These are reports that calculate the percentage of completion of the project in its entirety, in accordance with the project’s description and definition as held by the Real Estate Development Guarantee Accounts Department and the Surveying Department. The overall report must be published on the Department’s official ‘De Rest’ application.
  2. Partial reports are specific reports relating to a particular part of a larger project (for example, a single villa out of a project comprising 100 villas). Partial reports are not published on De Rest or the Department’s website.
  3. Infrastructure reports: These cover the infrastructure of a specific project, excluding buildings.
  4. The Spatial Planning Department can develop new reports based on the requirements of future projects approved by the relevant authorities. Fees are calculated in accordance with the legislation in force and may be updated from time to time; this is beyond the scope of this guide.

Chapter 8: Spaces

The types of approved spaces are:

  1. Building area
  2. Land area

Best practices:

The Department calculates floor areas in accordance with its own standards, which are based on the best international standards specialising in the calculation of floor areas.

Chapter 9: Project Description and Scope

Reporting the percentage of project completion is of great importance in the management of performance bonds for property projects. For this reason, and for engineering and technical reasons, the scope of property projects must be defined to ensure the accuracy of calculations and to safeguard the rights of all parties. The Real Estate Regulatory Agency is responsible for approving projects, as well as defining the project specifications and the number of units.

To ensure accuracy in calculating completion rates, we recommend that the number of villas in any single project should not exceed 250, nor should the number of independent buildings exceed four. This is to ensure the accuracy of the technical reports prepared by the Department, which are used by the relevant authorities to monitor the project financially. The project description, the number of units, buildings or plots of land, and their areas may not be altered without the prior approval of the Authority and the Land Administration Department.

Chapter 10: Formal Working Procedures

(To explain the tasks and steps, not the time taken to carry out the procedure)

Chapter 11: Outputs

Key outcomes of the project include:

1. Register for calculating the percentage of completion (with an example for clarification):

Specialist construction worksWeightDate of last visit to the projectDate of current visit
Engineer’s nameEngineer’s name
Site-specific achievementTotalSite-specific achievementTotal
تجهيز الموقع Site Mobilization2.00100.00%2.00100.00%2.00
تفعيل الأرض و Enabling works تسوية التربة3.00100.00%3.00100.00%3.00

The weights must be set during the first site visit to the project, based on the cost of each project component, and may not be altered until the project is completed (except in exceptional circumstances, subject to the Department’s approval). The on-site completion percentage is calculated in accordance with (Title 3: Basis for Calculating the Completion Percentage).

  1. Technical Report: This is the official report issued by the Department’s electronic system and includes the Register showing the percentage of completion referred to above, the project number, the plot number, the project name, the date of...