Answer: No. If the developer exercised their contractual right to extend the completion period with notice and delivered the unit within the agreed extended period, and the delay is minimal and justified by the nature of real estate development, they are not liable for delay damages.
Legal Basis:
Article 246, 257, 272 of Civil Transactions Law (Federal Law No. 5 of 1985):
Relevant Case Law:
Case No.458 of 2025 / Dubai Court / Real Estate