FAQ: Contractor Suspends Works, Misuses Advance Payment, and Delivers Non-Compliant Work — Employer's Rights and Remedies

Status

In force

Issuing Authority

realLaw Team

CONTEXT

If a contractor has stopped work before completion, retained a substantial advance payment, and the work performed does not meet contractual specifications, the employer has formal legal remedies — including judicial termination of the contract, recovery of overpayments, and compensation for the cost of engaging a replacement contractor. The strength of the claim depends heavily on technical documentation prepared before legal proceedings begin.

 

LEGAL BASIS

  • Federal Law No. 5 of 1985 on Civil Transactions (in force until 1 June 2026)

  • Dubai Law No. 13 of 2008 on Interim Real Estate Register (off-plan property only, as amended)

  • Dubai Law No. 8 of 2007 on Escrow Accounts for Real Estate Developments (off-plan property only)

 

TWO DISTINCT SCENARIOS

 

Scenario A — Private Construction or Renovation Contract

A contract between an employer and a private contractor for works on an existing property. Governed by the Civil Code provisions. Disputes are pursued through ordinary civil court proceedings.

 

Scenario B — Off-Plan Property Purchase from a Developer in Dubai

Governed by Dubai Law No. 13 of 2008 and Dubai Law No. 8 of 2007 in addition to the Civil Code. Additional protections apply through the Oqood registration system and mandatory escrow account mechanism. Refer to our dedicated FAQ on off-plan property developer disputes for this scenario.

 

EMPLOYER'S RIGHTS UPON CONTRACTOR BREACH

Where the contractor has unilaterally suspended works without lawful grounds, or where performed works deviate from agreed specifications, the employer may claim:

  • Judicial termination of the contract

  • Recovery of advance payments proportionate to unperformed works

  • Compensation for the cost of engaging a replacement contractor to complete or remedy the works

  • Damages for losses resulting from delay or defective performance

  • Default interest where applicable

  • Enforcement of contractual penalties or retention provisions where included in the contract

 

STEP-BY-STEP: HOW TO PROCEED

 

Step 1 — Document the actual condition of the works

 

Before taking any formal steps, prepare a comprehensive record of the current state of the project:

  • Detailed inspection report describing all defects and deviations from the design and specifications

  • Photographic and video documentation of the condition of all works performed

  • Comparison of works actually completed against the contractual scope and timeline

This documentation is the foundation of all subsequent steps.

 

Step 2 — Engage an independent technical expert

 

Commission a report from a licensed engineer or independent technical expert assessing:

  • The quality of works performed

  • The actual volume of works completed relative to the contracted scope

  • The cost of remedying defects and completing unfinished works

This expert report will carry evidentiary weight before the court and should be prepared before any legal proceedings are initiated.

 

Step 3 — Serve a formal written notice on the contractor

 

Issue a written notice to the contractor specifying:

  • The contractual provisions breached

  • A detailed description of the defects and deviations identified

  • A calculation of the overpayment and damages claimed

  • A reasonable deadline for rectification or repayment

Written notice is a prerequisite for subsequent court proceedings and...