Emirates Research and Development Council Decision No. 01 of 2026 on the Pre-Approval of R&D Projects for the Purposes of Cabinet Decision No. 215 of 2025 and Ministerial Decision No. 24 of 2026

Status

In force

Issuing Authority

Emirates Research and Development Council

Effective date

14 Oct 2026


The Emirates Research and Development Council:

Has decided:

Article (1)
Definitions

Definitions in Federal Decree-Law No. (28) of 2022, Federal Decree-Law No. (47) of 2022, Cabinet Decision No. (142) of 2024, Cabinet Decision No. (215) of 2025 and Ministerial Decision No. (24) of 2026 referred to above shall apply to this Decision, other than that, the following words and expressions shall have the meaning assigned against each, unless the context requires otherwise:

Applicant: The Person required to apply for Pre-Approval under Article (3) of this Decision, being the Qualifying Entity or, where applicable, the Parent Company or the Domestic Designated Filing Entity.

Determination: The decision issued by the Council in respect of a Pre-Approval Application, being one of the outcomes specified in Article (7) of this Decision.

Expenditure Confirmation: The submission to the Council of the actual Qualifying R&D Activities undertaken and the actual Qualifying R&D Expenditure incurred in respect of a pre-approved R&D Project during the Tax Period or Fiscal Year to which the Pre-Approval relates, together with the average number of R&D Staff per R&D Project in the relevant Tax Period or Fiscal Year and the supporting technical documentation.

Notification: The communication of a notice, Request for Information, Determination, Reconsideration decision or other communication under this Decision by the Council to the Applicant.

Pre-Approval: The pre-approval issued by the Council in respect of an R&D Project confirming that the activities specified in the Pre-Approval Application constitute Qualifying R&D Activities and are capable of incurring Qualifying R&D Expenditure, in accordance with Cabinet Decision No. (215) of 2025 and Ministerial Decision No. (24) of 2026.

Pre-Approval Application: The request for Pre-Approval submitted to the Council in the form and manner specified by the Council.

Reconsideration: The procedure by which an Applicant may request the Council to reconsider a Determination in accordance with Article (10) of this Decision.

Rejection: The rejection issued by the Council in respect of an R&D Project that does not satisfy the applicable conditions of Pre-Approval in accordance with Cabinet Decision No. (215) of 2025 and Ministerial Decision No. (24) of 2026.

Request for Information: A notice issued by the Council under Article (6) of this Decision requiring the Qualifying Entity to provide further information, or documentation before a decision of the Council is made under the relevant Article.

TAWWER: The electronic system known as "TAWWER" designated by the Council for the administration of Pre-Approval matters under this Decision, or any successor or replacement system designated by the Council.

Article (2)
The Pre-Approval Requirement and the TAWWER platform
  1. A Qualifying Entity shall obtain Pre-Approval from the Council for each R&D Project in respect of which the R&D Tax Credit is claimed, in the form, manner and within the timeline specified by the Council, in accordance with Clause (1) of Article (4) of Ministerial Decision No. (24) of 2026.
  2. The TAWWER platform shall be the only channel for the administration of the Pre-Approval process under this Decision, including the submission of Pre-Approval Applications, the issuance of Requests for Information, the issuance of Determinations and Pre-Approvals, the submission of Expenditure Confirmations, the submission of Reconsiderations, and all related Notifications, unless the Council specifies otherwise.
  3. A Determination, Request for Information, Notification or other communication issued through the TAWWER platform shall be deemed issued and notified to the Applicant on the date on which it is made available to the Applicant on the platform, and a Determination shall take effect on that date.
  4. Where the TAWWER platform is unavailable or its use is not practicable, the Council may specify alternative means of submission, Notification or other communication with the Applicant, and the Council may extend any timeline under this Decision accordingly.
  5. The R&D Tax Credit shall not be claimed in respect of an R&D Project unless both of the following have been completed: a) Pre-Approval has been obtained in accordance with Clause (1) of Article (4) of Ministerial Decision No. (24) of 2026; and b) the Expenditure Confirmation has been submitted in accordance with Clause (2) of Article (9) of this Decision, and the Pre-Approval has not ceased to have effect under that Article.
Article (3)
Submission of Pre-Approval Application and Representation
  1. The Pre-Approval Application shall be submitted by the Qualifying Entity, except as provided in Clauses (2), (3) and (4) of this Article.
  2. Where the Qualifying Entity is a member of a Tax Group, the Parent Company shall be responsible for applying for Pre-Approval, in accordance with Clause (9) of Article (13) of Ministerial Decision No. (24) of 2026.
  3. Where the Qualifying Entity is not subject to Corporate Tax and is a Constituent Entity, Joint Venture or JV Subsidiary of a Domestic Group that has appointed a

Domestic Designated Filing Entity, the Domestic Designated Filing Entity shall be responsible for applying for Pre-Approval, in accordance with Clause (8) of Article (14) of Ministerial Decision No. (24) of 2026.

  1. A Pre-Approval Application may be submitted on behalf of the Qualifying Entity or, where applicable, the Parent Company or the Domestic Designated Filing Entity, by its Legal Representative, an authorised representative, or a Tax Agent registered with the Authority, provided that the relevant authorisation is submitted to the Council.

  2. Any act performed by an authorised representative or Tax Agent within the scope of the authorisation shall be treated as performed by the Qualifying Entity, the Parent Company or the Domestic Designated Filing Entity, as applicable.

  3. Where any act is performed by a Legal Representative, the Legal Representative shall be responsible for compliance with this Decision, in accordance with Federal Decree-Law No. (28) of 2022.

Article (4)
Timeline and Manner of Submission of the Pre-Approval Application
  1. A Pre-Approval Application shall be submitted within the timeline specified in Clause (2) of this Article.

  2. A Pre-Approval Application shall be submitted within the following timeline:

    a. Where the Tax Period or Fiscal Year for the Qualifying Entity ends on or before 31 December 2026, within (40) forty business days from the end of the Tax Period or Fiscal Year.

    b. Where the Tax Period or Fiscal Year ends after 31 December 2026, on or before the last day of that Tax Period or Fiscal Year.

  3. A separate Pre-Approval Application shall be submitted for each R&D Project.

  4. For an R&D Project continuing across more than one Tax Period or Fiscal Year, a Pre-Approval Application shall be submitted for each such Tax Period or Fiscal Year for which the R&D Tax Credit is to be claimed, in respect of the Qualifying R&D Activities undertaken during that Tax Period or Fiscal Year.

  5. More than one Pre-Approval Application may be submitted in respect of a Tax Period or Fiscal Year.

  6. The Council may accept a Pre-Approval Application submitted after the timeline specified in Clause (2) of this Article in exceptional circumstances.

Article (5)
Form and Content of the Pre-Approval Application
    1. A Pre-Approval Application shall be submitted to the Council in the form and manner specified by the Council and shall contain all of the following:
    2. a) The particulars of the Qualifying Entity, or, where applicable, the Parent Company or the Domestic Designated Filing Entity, including legal name, Tax Registration Number and Tax Identification Number, trade licence details, registered address, and the details of any Legal Representative, authorised representative or Tax Agent.
    3. b) The Tax Period or Fiscal Year to which the Pre-Approval Application relates.
    4. c) A project document of the R&D Project to which the Pre-Approval Application relates.
    5. d) In respect of each R&D Project, a description of the activities that explains how they satisfy the conditions of Article (3) of Ministerial Decision No. (24) of 2026.
    6. e) A schedule of the R&D Staff engaged in the Qualifying R&D Activities, including roles, the location of the R&D Staff when performing the Qualifying R&D Activities, and time allocation.
    7. f) A schedule of the estimated expenditure in respect of each category of Qualifying R&D Expenditure set out in Article (5) of Cabinet Decision No. (215) of 2025 and Articles (8) to (11) of Ministerial Decision No. (24) of 2026.
    8. g) The supporting technical documentation available at the date of the Pre-Approval Application.
    9. h) A declaration made on behalf of the Qualifying Entity or, where applicable, the Parent Company or the Domestic Designated Filing Entity, confirming that the information provided is accurate, complete and not misleading, and confirming that the expenditure to which the Pre-Approval Application relates satisfies, and is expected to continue to satisfy, the conditions of Clause (3) of Article (5) of Cabinet Decision No. (215) of 2025.
    10. i) Where relevant, details of any subcontracting arrangement or Cost Contribution Arrangement relating to the R&D Project, including the parties to it.
    11. j) Any other information or documentation specified by the Council.
Article (6)
Review of the Pre-Approval Application and Request for Information
  1. The Council shall review each Pre-Approval Application to assess whether each R&D Project satisfies the conditions of Cabinet Decision No. (215) of 2025 and Ministerial Decision No. (24) of 2026.
  2. Where the Council requires further information or documentation before making a Determination, the issuance of a Request for Information shall be mandatory. The Applicant shall respond within (20) twenty business days from the date of Notification of the Request for Information, or such longer period as the Council may specify.
  3. Where the Applicant does not respond to a Request for Information within the period specified in Clause (2) of this Article, the Council shall issue a Determination of Rejection in respect of the R&D Project concerned, on the basis that the information required to make a Determination has not been provided.
  4. The Council may issue more than one Request for Information in respect of a Pre-Approval Application, provided that Requests for Information shall be limited to what is reasonably required to make a Determination.
  5. An Applicant may submit to the Council a request for amendment or withdrawal of a Pre-Approval Application at any time before a Determination is issued.
  6. A withdrawn Pre-Approval Application shall be treated as not having been submitted. The withdrawal does not preclude the submission of a new Pre-Approval Application...