Dubai Ports Authority Regulation PM - 18.0 Tanker Terminal and Vessel Safe Operation Regulation

Status

In force

Issuing Authority

DPA

UNIT I - Introduction 

18.1 Introduction 

This regulation forms an integral part of the Marine Operations procedural framework and is intended to provide comprehensive guidance to all users of live tanker berths within Dubai Ports. It outlines the necessary standards to ensure safe, secure, and efficient operational activities at tanker berths, particularly at the Port of Jebel Ali. 

 

The provisions of this regulation are articulated in broad terms to enable flexible application across various operational scenarios and to define the responsibilities of all stakeholders involved in tanker berth operations. 

 

A fundamental principle of effective safety management is leadership commitment. The outcomes in safety, health, and environmental protection are directly influenced by the dedication, competence, and proactive engagement of personnel at all organizational levels. 

 

While every effort has been made to ensure the accuracy and completeness of this document, PCFCDPA accepts no liability for any errors, omissions, or consequences arising from the use of this regulation. Updates and amendments to operational conditions or procedural requirements may be introduced without prior notice and will be reflected in future revisions of this document. 

 

This regulation does not override or replace existing requirements set forth by the International Maritime Organization (IMO), federal or local authorities. Users are expected to comply with all applicable statutory obligations and directives. 

 

For further guidance, reference should be made to the International Safety Guide for Oil Tankers and Terminals (ISGOTT) and other relevant international best practices. 

 

UNIT II - Tanker Berth Safe Work Permit (E-Permit)  

18.2 Tanker Berth Safe Work Permit 

18.2.1 Introduction 

18.2.1.1 Scope and Application 

This regulation establishes the Permit to Work (PTW) system applicable to operations at tanker berths. It sets forth the standardized format, regulatory framework, and procedural requirements for the issuance, management, and control of work permits. The objective is to ensure the safe planning and execution of all non-routine and potentially hazardous activities conducted within tanker berth areas. 

 

18.2.1.2 Purpose of the Permit to Work System 

The Permit to Work (PTW) system is a formal, written authorization that permits designated personnel to carry out specific work activities. It serves to identify and communicate potential hazards associated with the task and outlines the necessary safety precautions and control measures to ensure the work is performed safely. 

 

The PTW ensures that all risks are properly assessed and mitigated before the commencement of any activity, reinforcing a structured approach to hazard management and safe work execution within the tanker berth environment. 

 

18.2.1.3 Applicability 

The PTW system shall be applied to all non-routine operations conducted by berth users, port business units, or contractors. These include, but are not limited to, activities such as maintenance, inspection, testing, alterations, construction, modification, cleaning, dismantling, photography. 

 

18.2.1.4 Examples of Non-Routine Work Requiring a Safe Work Permit 

The following activities shall not be initiated at tanker berths without an approved Work Permit: 

18.2.1.4.1 Hot Work – Any activity involving open flames or generation of heat/sparks (e.g., welding, cutting, grinding). 

18.2.1.4.2 Spark-Inducing Tools or Equipment – Use of tools that may act as ignition sources in hazardous areas. 

18.2.1.4.3 Construction Activities – Including civil, structural, or mechanical works. 

18.2.1.4.4 Berth Survey and Project Operations – Specialized works associated with infrastructure assessment or project implementation. 

18.2.1.4.5 Opening of Process Equipment – Disconnection or breach of any pipeline, vessel, or equipment that contains or may contain flammable, toxic, or pressurized substances. 

18.2.1.4.6 Confined Space Entry – Entry into tanks, chambers, voids, or other restricted areas where atmospheric hazards may exist. 

18.2.1.4.7 Electrical Work – Maintenance or repair of electrical systems or energized equipment. 

18.2.1.4.8 Use of Radioactive Materials – Any operation involving radiography or radioactive sources. 

18.2.1.4.9 Preventive Maintenance  

18.2.1.4.10 Vehicle Entry – Movement of vehicles into restricted or hazardous berth areas for operational or maintenance purposes. 

18.2.1.4.11 Photography. 

18.2.1.4.12 Diving. 

 

18.2.1.5 Work Permit Requirements and Conditions 

18.2.1.5.1 Permit Details and Scope Each Work Permit shall clearly specify: 

- The exact equipment and work area involved; 

- The defined scope and nature of the work to be performed;

- The safety conditions and precautions to be observed; 

- The duration of the permit’s validity. 

Both the permit issuer and the work executor must jointly ensure that all safety requirements are satisfied before initiating the task. 

18.2.1.5.2 Non-Compliance and Withdrawal 

If any specified condition of the Work Permit is not met or cannot be fulfilled, the permit shall be considered invalid and must be withdrawn immediately. No work shall commence or continue under such circumstances. A new permit may only be issued once all deficiencies are rectified and verified. 

18.2.1.5.3 Pre-Issuance Site Verification 

Prior to issuing a Work Permit, the responsible authority must conduct a thorough assessment of the work site and equipment to confirm that all safety conditions are in place and the environment is deemed safe for the proposed activity. 

18.2.1.5.4 Emergency Vehicle Access to Tanker Berths 

Fire trucks, firefighting vehicles, and ambulances are exempt from the requirement to obtain a Work Permit when responding to emergencies. However, their crews and drivers must exercise the highest level of care and caution while operating within tanker berth areas to mitigate the risk of fire, explosion, or other hazards. 

All fire and ambulance vehicles must be equipped with the minimum required safety installations prior to entering the berth. For specific equipment requirements and access conditions. 

 

18.2.2 Objectives of the Tanker Berth Safe Work Permit System

The primary objectives of implementing the Safe Work Permit system at tanker berths are as follows: 

18.2.2.1 Authorization of Non-Routine Work 

To ensure that all non-routine and potentially hazardous work activities are formally reviewed and authorized prior to commencement. 

18.2.2.2 Hazard Awareness and Risk Mitigation 

To ensure that all personnel involved in the execution of the work are fully informed of the associated hazards, risks, and required safety precautions. 

18.2.2.3 Operational Awareness and Coordination 

To ensure that the responsible personnel overseeing jetty operations are fully aware of the nature, location, and timing of the work being carried out within their area of control. 

18.2.2.4 Documentation and Accountability 

To provide a formal, written record confirming that a competent and authorized individual has reviewed the proposed method of work and verified the adequacy of the control measures. 

18.2.2.5 Verification and Oversight 

To enable a secondary level of review, where necessary, in order to reduce the likelihood of errors in judgment or unsafe work practices that may increase risk. 

 

18.2.3 Authorization of Tanker Berth Safe Work Permit System 

18.2.3.1 General 

18.2.3.1.1 Issuance Authority 

Work Permits may only be issued by individuals who are formally authorized by PCFC-DPA. Typically, supervisors or higher-ranking personnel are nominated as authorized signatories by the General Manager of the respective berth user company, following verification of their qualifications, relevant training, and demonstrated competency. 

18.2.3.1.2 Scope of Authorization 

Management retains the right to limit the scope of an authorized signatory’s authority, restricting it to specific types of work or designated tanker berth areas. 

18.2.3.1.3 Segregation of Duties 

No individual may serve as both the issuing authority and the performing authority for the same work permit. Furthermore, the issuing and performing authorities must belong to different departments to maintain independence and oversight integrity. 

18.2.3.1.4 Typical Role Assignments 

The issuing authority is generally a supervisor or higher-level representative from the Operations Department. The performing authority is typically a supervisor or higher-level representative from the Maintenance Department or the relevant executing party. 

18.2.3.1.5 Gas Inspector Role 

The Gas Inspector must be a qualified representative from the Operations or Safety Department. This individual is prohibited from acting as the performing authority on the same work permit to avoid any conflict of interest. 

 

18.2.3.2  List of Authorized Signatories 

18.2.3.2.1 Issuing Authority 

A Supervisor or above who is qualified, trained, experienced, and deemed competent to issue Work Permits. The Issuing Authority must be formally authorized by PCFC-DPA, the Berth User Company, or the Business Unit (BU), depending on the operational context. 

18.2.3.2.2 Performing Authority 

A Supervisor or above who is qualified, trained, experienced, and competent to receive Work Permits and ensure the safe execution of the permitted activity. The Performing Authority must be formally authorized by PCFC-DPA, the Berth User Company, or Business Unit (BU), or the Contractor depending on the operational context. 

18.2.3.2.3 Competent Authority 

Designated representatives from PCFC-DPA who are responsible for oversight, compliance verification, and enforcement of relevant safety and operational regulations. 

18.2.3.2.4 Gas Inspector 

A certified Gas Tester who is qualified, trained, experienced, and competent to conduct gas detection and atmospheric testing. The Gas Inspector must be authorized by PCFC-DPA, the Berth User Company, or Business Unit (BU), or be a PCFC-DPA approved third-party surveyor (CAT B). 

 

18.2.3.3 Training and Authorization of Permit Signatories 

18.2.3.3.1 Mandatory Training 

All personnel designated as Authorized Signatories must complete the PCFC-DPA Tanker Berth Safe Work Permit Training to be eligible for approval. Upon successful completion, participants will be issued an official Tanker Berth Identity Card, which must be presented to the Berth Security Officer or Competent Authority for verification prior to undertaking any work. (Refer to Procedure PCFC-DPAPS-CP-01) “Tanker Berth SAFE Work Permit Training”.

18.2.3.3.2 Identity Card Specification 

The Identity Card will explicitly indicate the individual’s authorized role—whether as Issuing Authority, Performing Authority, or Gas Inspector—in accordance with their validated competency. 

18.2.3.3.3 Permit Presentation Requirement 

All Safe Work Permits must be fully completed and signed, and must be accompanied by the relevant Identity Cards at the time of submission for work commencement. 

18.2.3.3.4 Enforcement of Compliance 

Entry to the tanker berth and execution of work will be strictly prohibited for any unauthorized personnel or individuals found non-compliant with this training and identification requirement. 

18.2.3.3.5 Validity and Renewal 

Tanker Berth Identity Cards are valid for a period of two years. To maintain authorization, signatories must attend a refresher training course prior to the expiry of the card for revalidation. 

 

18.2.4 Work Permit Validity Period 

18.2.4.1 Permit Duration 

Work Permits issued for cold work, hot work, vehicle entry, vessel entry, and construction activities shall be valid for a single shift only, not exceeding 12 hours, and must be aligned with the duty hours of the Performing Authority. 

 

Extensions beyond this period require submission of a duly completed Renewal Sheet, and must strictly adhere to the original safety precautions and conditions as specified in the initial permit. 

 

18.2.4.2 Daylight Work Limitation 

Work within the tanker berth is permitted only during daylight hours. In cases where work must continue into night hours, a No Objection Certificate (NOC) must be obtained in advance from PCFCDPA.

 

18.2.4.3 Right to Suspend or Revoke Work 

The following authorities retain the right to suspend or terminate any ongoing work at the tanker berth at any time, especially in the event of unsafe conditions or non-compliance with permit stipulations: 

1. Issuing Authority. 

2. Competent Authority. 

3. Security Department.

4. Marine Department. 

5. Dubai Civil Defence.  

6. Emergency Response Team (ERT). 

7. Such actions may be taken without prior notice if deemed necessary to maintain safety and regulatory compliance. 

 

18.2.5 Work Permit Procedures 

18.2.5.1 Types of Work Types of Work Requiring a Permit 

The Safe Work Permit system at the tanker berth categorizes work into several types based on associated hazards and required precautions. Each category must be clearly indicated by ticking the relevant box on the permit form. 

18.2.5.1.1 Cold Work 

A Cold Work Permit is required for activities involving equipment or machinery where hazardous materials may be present, but which do not involve any sources of ignition, flame, or heat generation. Examples include mechanical maintenance, non-intrusive inspections, and operations that do not pose a fire or explosion risk.

Note: “Cold Work” box must be selected on the permit. 

18.2.5.1.2 Hot Work 

A Hot Work Permit is mandatory for operations that involve or may generate heat or ignition sources sufficient to ignite flammable gas mixtures. This includes: 

- Welding, cutting, grinding, soldering, and burning. 

- Use of blow torches and heat guns. 

- Use of portable electrical/electronic equipment/tools that are not intrinsically safe or not explosion-proof. 

Additional guidance: 

If welding is a part of a broader task, a Cold Work Permit may be required for preliminary work, followed by a Hot Work Permit for the welding phase. 

Upon completion of hot work (e.g., welding), the Hot Work Permit shall be cancelled, and the job may continue under a valid Cold Work Permit. 

For work on electrical or electronic systems, an Electrical Isolation Permit from the Berth User is also required. 

Note: “Hot Work” box must be selected on the permit. 

18.2.5.1.3 Construction 

A Construction Work Permit applies to activities such as: 

- Projects includes Civil or Structural Work 

- Excavation 

- Demolition 

- Modification

- Erection

The permit process must ensure that all associated hazards are identified and that appropriate safety measures are implemented. 

Note: “Construction” box must be selected on the permit. 

18.2.5.1.4 Vehicle Entry 

A Vehicle Entry Permit is required for internal combustion or electrically powered vehicles/machinery entering the berth area, including: 

- Cranes

- Generators, Air Compressors. 

- Forklifts 

- Compactor

These permits are issued to manage and eliminate hazards associated with mobile equipment operating near flammable or sensitive zones. 

Note: “Vehicle Entry” box must be selected on the permit. 

18.2.5.1.5 Confined / Enclosed Space Entry 

A Confined Space Entry Permit is mandatory for any operation involving entry into a confined or enclosed space, or excavation exceeding 1.2 meters in depth. 

This permit ensures: 

- Atmospheric testing and confirmation of human-worthiness. 

- Implementation of rescue arrangements. 

- Compliance with confined space entry protocols 

Note: “Confined Space Entry” box must be selected on the permit. 

 

18.2.5.2 Preparation Requirements Before Work at Tanker Berths 

18.2.5.2.1 General 

18.2.5.2.1.1 Authorized person (Gas Inspector) prior to the issue of the Hot Work/Vehicle Entry/ Vessel Entry permit shall carry out a Gas Test. 

18.2.5.2.1.2 If hot work is not started within One Hour of satisfactory gas test, or has been Discontinued for that period of time, then other test shall be carried out unless specifically authorized by the issuing authority and / or the performing authority. Gas Tests shall be done on periodic intervals do not exceed 4 hours. 

18.2.5.2.1.3 Gas inspector shall maintain a written record for interval gas measurement readings. 

18.2.5.2.2 Preparation before Cold Work 

18.2.5.2.2.1 Lines, valves, and any other equipment may have to be completely depressurized and drained before work on them can be started. 

18.2.5.2.2.2 Connected piping may require isolation by blinding. All necessary bleeders and vents shall be opened. 

18.2.5.2.3 Preparation before Hot Work 

18.2.5.2.3.1 Owing to the high risk at a tanker berth, which is potentially a hazardous area any work must be strictly controlled. This control is achieved through the hot work permit system, which is applicable to all tanker berths. 

18.2.5.2.3.2 The persons authorized to issue hot work permits are personally responsible for ensuring that the site, the equipment, vessels, lines or other equipment covered by the permit are properly prepared to eliminate the risk of fire explosion or exposure to toxic gases. 

18.2.5.2.3.3 Any precautions required must include such items as: 

- Disconnecting lines, blinding and isolation. 

- Freeing the equipment of product and/ or gases. 

- Cleaning and removal of flammable/ combustible materials. 

- Determining the suitable location for welding or other hot work equipment. 

- The covering of sewers, ditches or drains/ vents etc. 

- Removal or wetting down of scaffolds, decks and platforms. 

- Making provision for fire protection and fire guards as appropriate/ necessary. 

18.2.5.2.4 Preparation before Vehicle Entry 

18.2.5.2.4.1 Hazards from mobile vehicles and machinery, other than the operating hazards such as lifting, digging, pulling etc., evolve mainly from the diesel engine power source. The hazards from the diesel engine include: 

- Exhaust fumes. 

- Exhaust sparks. 

- Ignition hazard from the starting system and electrical equipment. 

- Engine over speeding. 

- High surface temperatures. 

18.2.5.2.4.2 Precaution taken to deal with the hazards depends on the conditions under which the vehicle or machinery is to be operated. As there is always possibility of flammable gases occurring at the tanker berth, diesel engine installation should be equipped with the following: 

- Spark arrestor on the exhaust system. 

- A mechanical starting system, pneumatic or hydraulic or mains powered electric flameproof starter. 

- Certified flame proof/ explosion proof and intrinsically safe electrical equipment. 

- A flame arrester downstream of the air intake shut-off device further down stream.

- The engine control system should provide automatic shutdown of the engine, by closing the intake shut-off device, in the...