Dubai Executive Council Decision No. 46 of 2014 Concerning the Connections of Generators of Electricity from Solar Energy to the Power Distribution System in the Emirate of Dubai

Status

In force

Issuing Authority

Dubai Executive Council

Effective date

31 Dec 2014

We Hamdan bin Mohammed Bin Rashid Al Maktoum, the Crown Prince of Dubai and the Chairman of the Executive Council of Dubai,

After perusal of:

i. Federal Act No. 2 of 1994 Concerning Protection of General Network of Electricity and Water Services;

ii. Federal Law No. 3 of 2003, concerning the establishment of the Executive Council,

iii. Federal Law No. 19 of 2009 Establishing the Supreme Council of Energy;

iv. Dubai Law No. 6 of 2011 Regulating the Participation of the Private Sector in Electricity and Water Production in the Emirate of Dubai; and

v. Dubai Decree No. 1 of 1992 Establishing the Dubai Electricity and Water Authority and its amendments;

vi. Dubai Decree No. 22 of 2009 concerning Special Development Zones in the Emirate of Dubai.

vii. Dubai Executive Council Decision No. 2 of 2010 on the Establishment of a Regulatory and Supervisory Bureau for the Electricity and Water Sectors in Dubai;

and the legislations regulating the Free Zones in Dubai;

Resolved the following:

 

Article 1 - Definitions

The following words and expressions in this decree shall have the meaning indicated opposite each of them, unless the context implies otherwise:

 

Emirate: The Emirate of Dubai.

 

Council: The Supreme Council of Energy.

 

Authority: Dubai Electricity and Water Authority.

 

CEO: The Managing Director and Chief Executive Officer of Dubai Electricity & Water Authority

 

Transmission System: The system belonging to the Authority which entirely or mainly comprises the High-voltage electricity cables, lines and electricity installations and facilities owned and/or operated by the Authority and used to transmit electricity from a power unit to a power substation or other electricity generation unit

 

Connection: The connection of the production unit with the Distribution System.

 

Generator of Electricity: A generating unit or units that generate electricity exclusively from Solar Energy connected under one Consumption Account.

 

Distribution System: The electrical network at 33kV and below, and its components which are owned and operated by the Authority with the main purpose of delivering electricity to consumers from the Power Transmission System, including but not limited to all associated equipment such as lines and cables, electrical substations, pole mounted transformers, analogue electrical elements such as resistors, inductors, capacitors, and switches.

 

Solar Energy: The radiant light energy emitted by the Sun.

 

Person: Natural or legal person whether public or private

 

Producer: Any person that generates electricity from solar energy and connects it to the Distribution System as per terms and conditions of this Decision, excluding the Authority.

 

Consumption Account: The account of specific premise for metering the electricity imported from distribution system by a Meter dedicated for such purpose.

 

Import Electricity: Electricity that is drawn from the Power Distribution System and consumed by the Producer under one or more Consumption Accounts held by the Producer within the Plot.

 

Export Electricity: Electricity that is generated by the Producer and injected into the Power Distribution System by Generator of Electricity.

 

Surplus Electricity: The excess of Export Electricity over Import Electricity in an applicable billing period.

 

Connection Agreement: The agreement between the Authority and a Producer, which stipulates the terms and conditions for the operation of a Generator of Electricity and its connection into the Power Distribution System.

 

Annual Connection Cap: The maximum electricity generation capacity from Solar Energy that may be connected to the Power Distribution System in a calendar year, as determined by the Authority.

 

Connection Conditions: The requirements and standards of the Authority, including health, safety and environmental quality standards to be fulfilled by the Producers in order to connect the Generator of Electricity with the Distribution System.

 

Article 2 - Applicability of this Decision

1. The provisions of this Decision shall apply to all Producers who have any Consumption Account in the Emirate, including free zones and special development zones including Dubai International Financial Centre.

 

2. The provisions of this Decision do not apply on the projects or contracts subject to aforementioned Dubai Law No 6 of 2011.

 

Article 3 - Objective of this Decision

The objectives of this Decision are to:

1. Establish a clear legislative framework regulating the connection of Generators of Electricity to the Power Distribution System.

2. Contribute to fulfilling Dubai vision to become a smart city.

3. Encourage community members and entities to generate electricity from solar energy.

4. Contribute to diversifying energy sources, increasing the share of renewables in the electricity mix.

5. Contribute to environment protection, reducing the Emirate carbon emissions footprint.

6. Promote the growth of the Green Economy for Sustainable Development.

 

Article 4 - Powers of the Authority

For realising the objectives of this Decision, the Authority shall have the following powers and duties:

1. To set the general policy of generating electricity from solar energy in the Emirate and submit it to the Council for approval.

2. To determine the Annual Connection Cap.

3. To approve the Connection Conditions and review them regularly.

4. To approve Connection Agreement formats, review them regularly and entering into Connection Agreements with Producers.

5. To set the maximum generation capacity that can be exported by the Producer to Distribution System.

6. To determine the mechanism of carryover of Surplus Electricity which is being exported to the Distribution System

7. To monitor and ensure compliance of the Producer with the provisions of this Decision and Connection Agreement and to take appropriate action and measures against violating Producer.

8. To maintain and establish a register including all data and information related to the Producers in the Emirate.

9. Any other powers and duties for achieving the objectives of this Decision.

 

Article 5 - Connection to the Distribution System

It is forbidden for any person to connect his Generator of Electricity with the Distribution System without obtaining prior consent of the Authority and such consent shall be granted in accordance with Connection Agreement and the provisions of this Decision.

 

Article 6 - Connection Agreement

A. Any person who desires to connect his Generator of Electricity to the Distribution System shall submit an application, in a format prepared by the Authority, to enter into Connection Agreement with the Authority, attached with all the documents specified by the Authority.

 

B. The Producer may not transfer his rights or obligations in the Connection Agreement to third parties unless having obtained prior consent of the Authority.

 

Article 7 - Costs

All costs associated with the connection of a Generator of Electricity to the Power Distribution System shall be estimated by the Authority and considered as final and to be borne by the Producer.

 

Article 8 - Obligations of the Producer

A. The Producer shall comply with the following:

1. Obtain the approval of competent authorities in the Emirate for issuing buildings’ permits and classifying the usage of plots prior to the installation of the Production Units and to connecting them to the Distribution System.

2. Provide all necessary requirements and systems to install Generators of Electricity and connect it to the Distribution System including compliance with security and safety requirements, and providing electricity meters and necessary equipment required by the Authority.

3. Terms and conditions of the Connection Agreement, Connection Conditions, and any other relevant requirement adopted by the Authority.

4. Not to exceed the maximum generation capacity authorised by the Authority for exporting to the Distribution System.

5. Not to conduct any action impacting the safety and efficiency of the Distribution System.

6. Cooperate with the Authority staff in all matters related to the provisions of this Decision including metering the electricity exported to the Distribution System.

 

Article 9 - Consumption and export of Electricity

The following clauses shall be applied on the consumption and export of the electricity generated by the Generators of Electricity:

1. The electricity generated by the Generator of Electricity in the premise is to be consumed within the premises associated to one Consumption Account; in case the Producer holds more than one Consumption Account, it is to be consumed within any premises associated to the Consumption Accounts within the Plot.

2. Any excess electricity generated by the Generator of Electricity above the electricity consumed in the premise shall be exported to the Power Distribution System of the Authority in accordance with the provisions of this Decision and the Connection Agreement.

3. Offset against the units of the Import Electricity and the units of the Export Electricity within the same billing cycle associated with Consumption Account shall be processed, and...