Dubai Administrative Decision No. 64 of 2026 concerning the Regulations and Procedures and Deadlines for the Submission of the Progress report on the Project covered by the Partnership

Status

In force

Issuing Authority

Dubai Department of Finance

Effective date

04 Jun 2026

Director General of the Department of Finance

- Having regard to Dubai Law No. 5 of 1995 establishing the Department of Finance;

- Dubai Law No. 22 of 2015 regarding the Regulation of Public-Private Partnerships in the Emirate of Dubai;

- Dubai Decree No. 20 of 2009 appointing the Director General of the Department of Finance,

have decided:

 

Article 1 – Definitions

The words and phrases contained in this decision shall have the meanings assigned to them in the aforementioned Dubai Law No. 22 of 2015. For the purposes of this decision, the term “report” means: “the report on the progress of the project to be submitted to the Partnership Committee, in accordance with Article 34 of the aforementioned Dubai Law No. 22 of 2015”, and the phrase “Competent Department” shall mean: “the organisational unit within the government entity responsible for supervising the project”.

 

Article 2 – Contents of the Report

When the government body submits the report to the Partnership Committee, it shall ensure that the report is clear, accurate and comprehensive, and that it includes the following data and information:

1. A detailed statement on the progress of the project, including the percentage of completion achieved compared to the approved timeline.

2. Financial data and analyses illustrating the financial status of the project, including the budget status, a comparison of actual costs with approved estimated costs, and a statement of financial deviations and their causes, if any.

3. Results of the measurement of the project’s key performance indicators as specified in the partnership agreement.

4. An assessment of current and potential risks associated with the project, a description of the mechanism for managing and addressing them and the level of response to them, and an identification of the challenges and problems that have been identified, the measures taken in response to them, those that have not been addressed, and the reasons for this.

5. A statement of the results of the verification of the extent to which the project outputs comply with the approved quality standards and technical and operational requirements.

6. A statement of any obstacles hindering the implementation of the partnership contract, if any, and the proposed solutions to address them.

7. An executive summary addressing the most significant results and key achievements of the project, and recommendations regarding future steps and mechanisms for improving performance indicator results.

 

Article 3 – Procedures for Preparing and Submitting the Report

The following procedures shall be followed for the preparation...