Department: HSE
Document Identifier: DHCR/PP/HSE/004/01
This Risk Management (“RM”) policy has been prepared by DHCR HSE, and provides a clear policy on Risk Management Procedures.
1.1 Engaging in pro-active risk management activity, in addition to the process of assessing risk, will enable the early identification of many things that can go wrong as part of a systematic approach to risk assessment.
The Risk Management Programme employs a number of systems to identify potential risks. Research indicates that incidents are rarely due to individual failures but are usually associated with systems failures.
The purpose of this policy is to provide guidance to effectively identify and manage risk in conjunction with DHCR HSE procedures.
1.1 DHCC is committed to the continuous improvement of its risk management systems and has a positive and supportive approach to the management of healthcare risks. 1.2 Implementation of systems where possible to prevent harm and conduct activities in such a way as to ensure that all on campus are not exposed to unnecessary hazards through the provision and maintenance of equipment and premises which are safe and without unnecessary risks to health and safety. 1.3 Ensure that any premises under the control of the Business Partners / Investors are maintained in a condition that is safe, and without unnecessary risks to health and safety. 1.4 Business Partners / Investors are will incorporate in policies, procedures and guidelines the practical guidance given in best practice methods, which are relevant to any work of the organisation. In addition, where no “Best Practice Method” exists, the organisation will compile and apply its own policies, procedures and guidelines, appropriate to specific activities, in order to control the risks to patients, employees and others and provide for the protection and avoidance of damage to the environment.
1.5 Compliance with all Federal Law, Local Orders, Regulations and International best practice relevant to the Hospitals activities. 1.6 Business Partners / Investors are will carry out and act appropriately on risk assessments of current work practice methods, premises, plant, and equipment, to ensure risks are efficiently managed. 1.7 Will actively promote and encourage the involvement of employees in the organisations risk management practices and procedures. 1.8 Will provide such information, instruction, training and supervision as is necessary, to ensure that risk management is an integral part of every employees work, and to ensure that this policy is efficiently implemented. 1.9 Ensure that risk management matters are effectively addressed at all levels. 1.10 Provide information on risks and the appropriate protective and preventative Measures.
2.1 To demonstrate how to assess risk and establish a common approach for risk management with the following objectives: 2.1.1 Ensure as far as is reasonable practicable there is a program for risk assessment 2.1.2 Identify the hazards and risks in respect of the work activity 2.1.3 Provide a program for performance and the development of risk elimination
3.1 This policy applies to all, staff operating and applicable to all property (buildings owned or occupied) and premises including residential accommodation, and businesses) within the DHCC campus. 3.2 3.1.1 Every Business Partner and their staff including all contractors staff should adhere strict adherence to this DHCR Risk Management Policy 3.1.2 All new staff shall be oriented on the Risk Management Policy as part of general staff orientation program
3.1.3 It should be understood that the onus on all operating / working in DHCC to demonstrate compliance with the DHCC Regulatory Division Risk Management Policy
It is the objective of all Business Partners / Investors to effectively manage all risks who may be affected by the organization's activities through the implementation of a risk management system that will pay due attention to efficient:
4.1.1 Identification of hazards
4.1.2 Assessment of risks associated with these hazards
4.1.3 Development and implementation of control measures to eliminate these hazards or to reduce risks to acceptable levels
4.1.4 Evaluation to ensure that controls are effective, and monitoring of the ongoing change situation
4.1.5 Minimization of harm caused by adverse incidents
4.1.6 Incident reporting and investigation
4.1.7 Claims management
Each BP/Inv has a responsibility to ensure that there is a clear and appropriate management structure that enables risk to be identified at High Level and at operating Management Level and decisions to eliminate Harm are taken at an appropriate level.
The management of each BP/Inv will understand the risks associated with achieving its objectives and will actively reassess and monitor them. Progress against action plans and the residual risks will be an ongoing program.
Risks will be identified from risk assessments (reference to Appendix 6.1: Template Risk Assessments).
Risk Management Process, the management of risk is a key component in the safety management system within all organizations activities.
The risk management process is the systematic application of management policies, procedures and practices that determine the approach for communicating, identifying, assessing, monitoring and reviewing risks. This is a step-by-step approach that leads the user through from assessment of the activities they undertake, identification of risks through to the incident reporting process. The aim of risk assessment is to identify potential sources of harm and loss and put in place adequate controls or preventive measures before they result in an accident or illness. The key stages of Hazard Identification and Risk Assessment Survey are as follows:
In relation to all risks analyzed and assessed, dependent on the likelihood of occurrences, action should be taken as soon as possible to eliminate, reduce or transfer risks.
Each risk should be allocated to a risk owner/s that is responsible for acting appropriate action to minimize its impact/consequence.
Prior to commencing a Risk Assessment, an inventory of all work activities, processes, equipment and machines used must be prepared for each work area or location being assessed. It is vital to include infrequent maintenance tasks as well as more routine day-to-day work.
The management of risk is integral part of every process within each organization and is central to having a robust system of internal control. The following actions 5.1.1 – 5.1.3 should be completed in the Risk Assessment Template (reference to Appendix 6.1: Template Risk Assessments)
There are 3 x Steps to Analyzing the Risk
5.4.1 Identify the risk/Hazard
5.4.2 Analyze the Risk
5.4.3 Evaluate the Risks
Identify the situation or source with a potential for harm in terms of death, ill health, injury or damage to property.
Provide a description of the hazard providing detail on the persons at risk and/or consequence of the risk/hazard being realized
For each activity, material, equipment and machine, the hazards must be identified. A hazard checklist should be drawn up, taking into account the nature of work activities and locations where work is carried out
| Physical | Chemical | Biological | Psychological | Environmental, Mechanical/ Biomechanical |
|---|---|---|---|---|
| ▪ Excessive noise ▪ Extreme Temperatures ▪ Inadequate Lighting ▪ Ionizing radiation ▪ Lasers ▪ Electricity ▪ Tools ▪ Pressurized systems ▪ Improper ventilation ▪ Stairs/ladders ▪ Slipping / Tripping ▪ Pinch points ▪ Fire ▪ Working at heights. ▪ Workplace violence | ▪ Formaldehyde ▪ Xylene ▪ Acetaldehyde ▪ Phenols ▪ Hazardous drugs such as cytotoxic agents, ribavirin, pentamidine. ▪ Waste anesthetic gases ▪ Dust / Fumes ▪ Smoke ▪ Solvents ▪ Pesticides ▪ Paints ▪ Flammables ▪ Alkalis/Acids | ▪ Human immunodeficiency virus (HIV) ▪ Vancomycin resistant enterococcus(VRE) ▪ MRSA ▪ Hep. B virus ▪ Hep. C virus ▪ Mycobacterium ▪ Fungi/Molds ▪ Blood samples ▪ Body fluids ▪ Insects ▪ Plants | ▪ Stress ▪ Rotating shift work ▪ Prolonged working hours ▪ Sexual harassment ▪ Workplace violence ▪ Inadequate staffing ▪ Heavy workload | ▪ Tripping hazard ▪ Unguarded equipment ▪ Air quality ▪ Slippery floors ▪ Confined space ▪ Forceful exertions ▪ Awkward postures ▪ Localized contact stresses ▪ Vibration ▪ Repetitive / prolong motion ▪ Lifting/ moving patients ▪ Cluttered or obstructed work areas/ passageways |
Risk analysis is about developing an understanding of the risks identified. In subjecting a risk to analysis it is essential that account is taken of the existing must be recorded as, control measures. These include all measures put in place to eliminate or reduce the risk and may include;
All controls to minimize the risk that are currently in place should be listed on the risk assessment form. When listed, time should be taken to consider their adequacy (i.e. identify weaknesses in existing procedures and opportunities for error), method of implementation and level of effectiveness in minimizing the identified risk to the lowest reasonably practical level. It should be noted that management should not assume that the controls which rely on people following correct procedures will always work.
The risk associated with each hazard must then be assessed by determining who might be harmed and how. The assessment should evaluate the potential for harm and its consequences.
Consideration should be given to the number of persons exposed to the hazard, the frequency and duration of exposure to the hazard, potential failure modes and routes of exposure.
The consequences of harm could range from slight injury or illness to lacerations, fractures, amputations, chronic pain, poisoning, cancer or fatal injuries.
Risk depends on many, often related, circumstances:
The purpose of risk evaluation is to make decisions based on the outcome of the risk analysis regarding which risks require treatment and the priorities of that treatment. Depending on the risk rating and the adequacy of the current controls in place an evaluation is made whether to;
5.4.3.1 Accept the risk
5.4.3.2 Treat the risk by;
Avoiding
Transferring
Controlling
After assessing risks, it should be estimated that how likely it is that a hazard will cause harm and how serious that harm is likely to be. This will help in prioritizing different risks as high, medium or low and in deciding on the appropriate level of management effort and resources that will be required to control each hazard. It will also help to decide how urgent any corrective measure needs to be.
$$\text{Risk Factor} = \text{Likelihood} \times \text{Severity}$$
Rating of Likelihood:
| Likelihood | Definition | Rating |
|---|---|---|
| ▪ Improbable | ▪ May occur only in rare and exceptional circumstances. ▪ Happen once in 10 years | 1 |
| ▪ Unlikely | ▪ Is not likely to occur in normal circumstances ▪ More than once in 10 yrs. but not more than once in 5 years. | 2 |
Rating of Severity:
| Severity | Definition | Rating | |
|---|---|---|---|
| InsignificantMinorModerateMajorCatastrophic | Dealt with First Aid only.Non-serious equipment or facility damage.Medical help required (outpatient)Minor process loss or facility damage.Chemical release requiring only routine cleanup without reporting.Significant reversible injury. Overnight hospitalization (inpatient).Moderate process loss or facility damageChemical release triggering external reporting requirements.Extensive permanent injury/illness (eg. loss of fingers/toes), extended hospitalization.Major process loss or facility damageChemical release with temporary environmental or public health impact.One or more fatalities.Permanent disabling injury (e.g. loss of entire limb, blindness etc.)Entire process shutdown or extensive facility damage.Chemical release with acute, lasting environmental or public health impact | 12345 |
In relation to all risks analyzed and assessed, dependent on the likelihood of occurrences, action should be taken as soon as possible to eliminate, reduce or transfer risks.
Each risk should be allocated to a risk owner/s that is responsible for acting appropriate action to minimize its impact/consequence.
Prior to commencing a Risk Assessment, an inventory of all work activities, processes, equipment and machines used must be prepared for each work area or location being assessed. It is vital to include infrequent maintenance tasks as well as more routine day-to-day work.
The risk matrix below provides a visual picture of how to calculate the risk:
| Low | Medium | High |
The lowest risks are those in the GREEN boxes, which suggest the risk has been controlled to its lowest possible level.
The risks located in the AMBER boxes suggest that controls are adequate, but ongoing monitoring is required.
Those risks located in the RED boxes are classified as key risks and should receive early management attention and ongoing monitoring.
| RISK MATRIX 5 X 5 RISK RATING MATRIX TOOL | |||||||
|---|---|---|---|---|---|---|---|
| Low Risk | Green = 0 - 5 | Severity of the potential injury/damage | |||||
| Moderate Risk | Amber = 6 - 10 | ||||||
| Major Extreme | Red = 11 - 24 | ||||||
| Sentinel Event | Purple = 25 | Negligible (1) | Minor (2) | Moderate (3) | Major (4) | Extreme (5) | Risk Rating |
| Likelihood of the hazard happening | Almost Certain (5) | 5 | 10 | 15 | 20 | 25 | Sentinel |
| Likely (4) | 4 | 8 | 12 | 16 | 24 | High | |
| Risk Factor | Risk Rating |
|---|---|
| 1 to 5 | Low |
| 6 to 15 | Medium |
Risk ratings scores 1 - 5 – Low Risk
These risks in between 1 – 5, out of a score range 1 -25 are managed internally as low rated risks.
Risk rating scores of between 6 and 15 - Minor Risk
These risks in between 6 – 15, out of a score range 1 -25 are Minor Rating, managed internally, but reported to DHCR HSE.
These risks in between 16 – 24, out of a score range 1 -25 are potential for Major / Extreme Risk Rating, reported to DHCR HSE.
The risk with a score of 25, out of a score range 1 -25 are potential to lead to a Sentinel Event and must be reported to DHCR HSE, immediately.
Accepting the risk, a risk is called acceptable if it is not going to be treated, accepting a risk does not imply that the risk is insignificant. Risks in a service may be accepted for a number of reasons:
The level of the risk is so low that specific treatment is not appropriate within available resources
The risk is such that no treatment option is available. E.g. dependent on external factors such as government policy
The opportunity presented outweighs the treats to such a degree that the risk is justified.
Steps 1-3 (refer to 5.1.3 Evaluate the Risks) above conclude the Risk Assessment process, it is however essential that in terms of managing assessed risks that the treatment (Action) plan is put in place against those risks that have been evaluated as requiring treatment.
| Assessment | Description |
|---|---|
| Low | Acceptable as is it. No significant. |
| Medium | Acceptable with controls | ||
| High | Unacceptable and significant. |
There are three methods of treating the risk, these are;
5.12.1 Avoid the Risk
5.12.2 Transfer the Risk
5.12.3 Control the Risk
This is achieved by either deciding not to proceed with the activity that contains an unacceptable risk, choosing an alternative activity, which meets the objectives and goals of the Hospital, or choosing an alternative and less risky methodology or process within the activity
Risk transfer transmits the organization's risk to an outside party. The most common method being the purchase of insurance, the cost of which is dependent on the level of assurance provided to the insurer in terms of the level of risk of a claim occurring.
This is the most commonly used treatment option as it is focused on reducing...