Department: HSE
Document Identifier: PP/HSE/002/01
This CSC is a policy been prepared by DHCR HSE, and provides a clear mandate on Contractors Safety requirements.
DHCC Regulations Division, require that every Business Partner must ensure the protection of health and safety of contractors, subcontractors, workers, staff engaged 'construction', in the workplace.
1.1 The purpose of the Contractors Safety Code ("CSC") is a guidance for Business Partners ("BP") to direct attention to all contractors, regardless of the nature, duration, size of the fit out / construction work to ensure the safety management systems are in place, with effective management communication between all workers.
1.2. To ensure that guidance and policy exists for the safety of external contractors visiting / working on DHCC site, facilities, and immediate environment, this includes all commissioning, refurbishment / renovation, decommissioning and demolition activities, and ranges from occasional work such as window cleaning, to high risk work on reconstruction projects.
1.3 To ensure the protection of the health and safety of contractors, sub-contractors, employees, patients, visitors, vendors, and other users of all DHCC, as well as the surrounding communities and environment, and to reduce or minimize the risks from exposure to risks arising from contractor's activities
1.4 The CSC is intended for strict application by all contractors and all service providers during the pre, interim and post-delivery of works, regardless of the size, scale, duration of any works.
2.1 DHCR HSE is committed to provide guidance on the requirements of contractor's safety.
3.1 This CSC applies to all, healthcare facilities, facilities staff, patients, visitors, contractors, sub-contractors, service providers and others attending DHCC engaging with Contractors, Vendors, Service Providers or any contractual, maintenance obligations. The policy is applicable to all property (buildings owned or occupied) and premises including residential accommodation, and businesses), internal or external within the DHCC campus.
4.1 Compliance is mandatory for every contractor / service provider working on campus.4.2 All working with contractors / service providers have a duty to ensure, so far as is reasonable practicable, the health and safety of all, as reasonable possible, who operate, deliver a service to DHCC.4.3 Safety is everybody's business and the success of a health and safety systems is dependent on cooperation of all persons within each of the BP facility to cooperate.4.4 All contractors / service providers working on site must read this CSC, prior to any site works commencing and understand the health and safety arrangements for their particular site works and incorporate and integrate all their tasks in conformance with the established safety procedures for that particular task.4.5 Responsibility4.5.1 Every Business Partner and their staff including all contractors / service providers staff should adhere strict adherence to this CSC.4.5.2 All new Contractors shall be oriented on the CSS4.5.3 It should be understood that the onus is on all BP ensure compliance with CSC4.5.4 Every Business Partner and their staff including all contractors staff are required to report all occupational injuries, fire events, chemical spills, environment incidents to DHCR HSE Department.
| 5.1 | Safety Documentation Prior to any site works, the BP must ensure the contractor has the appropriate safety management system documentation: insurance, access to equipment maintenance records, scope of work, roles and responsibilities for the task, appropriate certifiable training (where appropriate), method statement and risk assessment (where required), site safety measures, evacuation procedures, incident reporting procedures, prior to site works commencing. |
| 5.2 | Specialist work requiring a Permit to Work (“PTW”) 5.2.1 The Permit to Work procedure is dependent on the procedures set down by the Building Facility Management Team / Property Managers and it is the Business Partner’s responsibility to ascertain the procedure prior to any site works. 5.2.2 For Works in DHCC owned buildings a Permit to Work is obtained from the DHCC Facilities Department, for all site works. 5.2.3 If the contractor is carrying out the following works, a Permit to Work is required: 5.2.3.1 Working at Height (Above 2 meters) 5.2.3.2 Isolation/Tag out/Lock out of Services 5.2.3.3 Work in Confined space 5.2.3.4 Hot work 5.2.3.5 Mechanical Lifting Devices 5.2.3.6 Work in restricted area (Medical Gas Areas/ Radiation (Infrared/ Ultrasonic / Microwave/ EM/ Radio Active Material)Areas/ Laboratory) 5.2.3.7 Deep Excavation/ Deep Penetration in to structures 5.2.3.8 Major Electrical Works 5.2.3.9 Work on Roof Top 5.2.3.10 Work on Scaffolds |
| works): 5.3.1.1 Final Design / Architect's Drawings 5.3.1.2 Civil Defence Certificates 5.3.1.3 Contractor's licenses and insurance policy 5.3.1.4 Method Statement and risk assessments 5.3.1.5 Any specialist Permit to Works 5.3.1.6 Competency / Training Certificates 5.3.2 The Contractor must submit the appropriate Liability Insurances and all Insurances shall be extended to indemnify the Building Owner / Business Partner / Investor for the specific site works in the event of negligence on behalf of the contractor against any claim for which the Contractors may be legally liable. | |
| 5.4 | Safety Work Assessment Any work activity, there should be an assessment of the risks and hazards of the task to ensure a full assessment of site works are completed in an effort to eliminate harm. This task must be undertaken by a competent member of staff from the Business Partner to ensure the contractor / service provider adhere to the CSC and eliminate harm. |
| consultation with the contractor and/or the facility manager for guidance and oversight review, prior to commencing or recommencing works, is required. | |
| 5.7 | Contractor arrival on site The Contractor must ensure their Senior Representative on site must have the required information (see above) ready for production to either the Building Management/Facilities Team and Business Partner and the DHCR HSE Regulator in the event of an inspection. |
| 5.10.1 Unauthorised access on without prior Building Management/Facility/Security team approval, may result in their site works being stopped. 5.10.2 Before commencement of any work, the contractor shall ensure that all its staff involved have been issued appropriate building access approval obtained from the 'Building Management Team' ('BMT') and this can only be used individually. 5.10.3 If an 'Entry Pass' is required it must be worn by all contractors and available for inspection by BMT. Security reserve the right to withdraw passes for deemed unsafe /dangerous acts. All contractors must return any identification/access cards/keys when their scheduled works are completed or by arrangement from the BMT. 5.10.4 All contractors must adhere to all regulations regarding the issuing of keys and usage of same. All access cards / keys must be returned to the location received once usage is complete BMT. 5.10.5 All contractors must adhere to all local security procedures, protocols and instructions while on site. | |
| 5.11 | Contractors Work Area 5.11.1 Contractors work area must be clearly defined. The contractors must ensure appropriate Safety signage, to identify the site, at the entrance of the site (for Fit Out Works). 5.11.2 The contractors segregated work area (for all works) is the responsibility of the contractor to control site access and ensure access is restricted to authorised persons only. Access to sites must be strictly controlled to prevent access by children or any unauthorised personnel. 5.11.3 All construction and maintenance work is to be isolated from other activities and public. Where this cannot be controlled by closing of areas to stop access temporary to the area, then barricades are required to be used. If at any stage during the construction or maintenance work, a chosen method of isolation found not to be successful, then appropriate additional controls must be implemented. |
| 5.11.4 Under no circumstances is construction or maintenance work to be carried out above or proximate to a workplace where harm may occur or that has potential to exposes others to an increased risk of the hazard. 5.11.5 The contractor must make the appropriate arrangements with the BMT prior approval provisions to shutdown of water, gas, fire alarms and electricity supplies in consultation with any external stakeholders e.g. Dubai Civil Defence, Dubai Municipality, DHCR HSE, where appropriate. | |
| 5.12 | Fire Activation In the event of a fire alarm activation within the contractor's work area, it may be necessary for BMT or security personnel to enter the location for alarm investigation and verification. For such instances a set of keys to access secured work areas are to be provided to the Security and BMT, at all times and the area must be left in a safe condition for access. |
| extinguisher. All combustible materials shall be cleared from the area before welding, cutting or burning. Hot work should only be undertaken at an agreed time with the BMT in consultation with the security personnel. 5.14.3 Upon completion of the fit-out work, all the existing fire alarm system shall be activated and tested for its effective compliance, in consultation with the BMT and Security Team. | |
| 5.15 | Contractors Fire Check 5.15.1 All contractor personnel upon arriving on site must check the following: 5.15.1.1 Nearest means of escape in the event of a fire 5.15.1.2 Location, type and method of operating fire – fighting equipment (Only if trained to do so) 5.15.1.3 Location of the nearest fire alarm - Break Glass Unit and Fire Alarm Panel 5.15.1.4 Procedure to be taken in case of fire or on the sounding of an alarm 5.15.1.5 Emergency contact numbers |
| 5.17.3 Disabling of a Fire Alarm Detection & Protection systems should only be carried out for the minimum period of time, with approval from the key stakeholders. 5.17.4 The method of Fire Alarm Control system disablement must be disabled / re-enabled, only be approved personnel and must only be disabled for the minimum duration and reconnected as soon as possible and must never be disabled out of hours, in accordance with the BMT procedures. All Business Partners, who are affected in the building must be put on notice of the Disablement, so they can revise their emergency preparedness. 5.17.5 If the Contractor activates the fire alarm they must immediately notify Building Management Team and security. | |
| 5.18 | Personal Protective Equipment (“PPE”) The contractor is responsible for providing his employees appropriate an individual personal protective equipment, dependant on the work activity and provide provisions for first aid. |
| 5.20.3 Break stone / concrete works the contractor must ensure the correct installation and maintenance of screens, dust screens, dust mats, local ventilation or enclosures by put in place and overseen and approved by the BMT (where appropriate). 5.20.4 Diesel or petrol operated equipment is prohibited. | |
| 5.21 | Electrical Equipment and Appliances 5.21.1 Contractors shall not interfere with or work on any of electrical installations prior to approval from Building Management Team. 5.21.2 A competent qualified Electrician must only carry out repair or installation of any electrical equipment. No temporary electrical supply shall be installed without the approval from Building Management Team. All cables shall be in good conditions with no evidence of exposed wires. 5.21.3 Contractors carrying out electrical work must have appropriate electrical installation standards; this applies to fixed installations and portable equipment. 5.21.4 Portable electric tools must be operated at 110 volts. Electrical connections supervised by the Building Management Team. 5.21.5 Contractor must ensure equipment has complete isolation, where 240 – volt of equipment is used it shall be protected by the source of supply by the suitable RCD. 5.21.6 Contractors must not enter sub-stations or switch rooms without approved by the BMT. 5.21.7 The contractor shall keep tag “Safe for use” on all electrical power hand tools in use. |
| 5.21.8 No power equipment shall be used without safety tag. All electrical leads should be connected to the power source through standard plugs and sockets in a good condition | |
| 5.22 | Chemical Safety 5.22.1 No chemical substances are to be stored on site. 5.22.2 The following chemicals: white spirit, adhesive glue, aerosol sprays are classified as flammable or extremely flammable, hazardous, explosive, corrosive, oxidising, toxic, harmful or dangerous to the environment and in relation to usage during works, must be outlined in the method statement and risk assessment. 5.22.3 Only sufficient amount of chemicals for a daily work are permitted. Contractors using oil base paints, varnishes and flammable material such as glue must supply fireproof storage for chemicals. 5.22.4 Contractors should use water based glues unless there is prior approval by the Building Management Team to use solvent based products. If solvent based products are used consideration must be assessed for the possible effects of fumes and vapours on patients and staff and the control measures must be outlined in the method statement and risk assessment. 5.22.5 All chemicals brought in by contractors or sub-contracts must be supported by a detailed site specific risk assessment, prepared in consultation with Building Management Team. 5.22.6 Storage facilities for hazardous substances must be approved from Building Management Team. Substances shall be held in a secure place with clear identification. The Contractor must remove all substances on site upon completion of the contract. 5.22.7 The contractor must provide copies of the Safety Data Sheets for all materials used in the contract and the safety procedures associated with such materials. 5.22.8 The contractor must ensure that their operatives are adequately supervised to |
| ensure their activities cause minimum disruption. | |
| 5.22.9 It is responsibility of the Contractor to ensure that his employee are properly informed and trained how to use and control hazardous substances. |
| 5.23.2.3 Bespoke safety management system 5.23.2.4 Bespoke Risk assessment 5.23.2.5 Bespoke Method Statement 5.23.2.6 Evidence of Certified training 5.23.2.7 Evidence of PPE 5.23.2.8 Evidence of PPM 5.23.3 The Permit is valid for the period stated and must be returned duly signed by on completion of the work. 5.23.4 The Contractor is responsible to notify Building Management Team, if they observe it necessary to isolate other areas or services on the site and to recommend any additions or extensions to the terms of the permit. 5.23.5 The Contractor must carry a copy of the Permit and / or display in the work location at all times on site. 5.23.6 The Contractor must ensure all of their staff, sub-contractors are aware of all Permits to Work and any restrictions, safety management systems, limitations, hazards contained in the permit. | |
| 5.24 | Hot Works 5.24.1 Hot works, include welding, thermal or oxygen cutting or heating and other related heat or spark producing operations which may cause smoke or fire, or which may trigger alarm in the fire detection systems. These works are significant Fire Hazard and extensive precautions and systems must be put in place prior to works. 5.24.2 Hot works for any maintenance or construction procedure are not to take place in any building without a Building Management Team hot work permit and the contract is overseen and duly notified to the Facilities, BMT and Security personnel. 5.24.3 A detailed specification of dry powder fire extinguishers shall be located within |
| the hot work area, outlined in the Risk Assessment and in accordance with the nature of the works. 5.24.4 Permits to work for Hot Work Permits is required for use of welding equipment, metal cutting torches, blow torches or any other naked flame. There must be a close control of sparks by the provision of necessary controls, with detailed safety systems outlined in the method statement and risk assessment. 5.24.5 At the end of the work a careful search of the surrounding area must be checked every 20 minutes, by a competent person, after completion of work that residual sparks or smouldering material are not left which could give rise to a fire. | |
| 5.25 | Working at Heights Where Contractors are involved in working at heights, any work / activity regardless of height where an employee could fall and suffer harm. A Safe Operating Procedures / Permit to Work at Heights must be completed and submitted to Building Management Team (see 5.1 and 5.3 above). |
| 5.27.3 All scaffoldings must be erected using sound materials in a good condition and supplied by approved scaffolding company. Contractor's Supervisor must ensure that the scaffolding is not overloaded. No one should stand or climb over scaffolding guardrails. No scaffolding shall be erected to obstruct normal access. Contractors are not allowed to erect or carry scaffolding near live overhead electrical cables. All scaffolds must be provided with suitable access. 5.27.4 All scaffolding working platforms, with the exception of the ladder access points, must be closed boarded, fitted with toe-boards, including stop ends and have double guardrails (top guardrails plus intermediate... |