Circular No. 19432 of 2007 on Marinas - Submission of Application for Marina Permit

Status

In force

Issuing Authority

Ports, Customs and Free Zone Corporation

Effective date

XX.XX.XXXX

Official Link

https://

To: All Business Units, Consultants, Project Managers, Engineers and Contractors.

Subject: Marinas - Submission of Application for Marina Permit.

Date: 22 July 2007

 

Please note below the new procedure to be followed by consultants for obtaining a Marina Permit for any Marinas or Small Craft Harbour development with effect from 01 September 2007. Please note that this requirement is specific to the marine side of developments and is over and above the standard requirements for Building Permits. The Application Process is comprised of three steps:

1. Pre-application meeting.

2. Preliminary / concept drawings to be submitted to CED for approval.

3. After receiving the concept approval from CED, the consultant shall obtain NOC from Marine Department by submitting documents as per their requirement(s). Simultaneously the consultant shall obtain NOCs from relevant service authorities. These Certificates can be common with the general Building Permit Application for the development but should refer specifically to areas earmarked for marina development.

4. Apply to CED for a Marina Permit by submitting d...