Head of the Department of Municipalities and Transport
- Having reviewed Abu Dhabi Law No. 1 of 1974 on the reorganisation of the government apparatus in the Emirate of Abu Dhabi, and its amendments;
- Abu Dhabi Law No. 3 of 2015 regarding the Regulation of the Real estate Sector in the Emirate of Abu Dhabi, and the Law amending it;
- Abu Dhabi Law No. 30 of 2019 on the establishment of the Department of Municipalities and Transport,
- Abu Dhabi Emiri Decree No. 11 of 2023 on the restructuring of the Executive Council of the Emirate of Abu Dhabi;
- Abu Dhabi Executive Council Decision No. 223 of 2023 regarding the Abu Dhabi Real estate Centre;
- Abu Dhabi Executive Council Decision No. 38 of 2024 regarding Bank Guarantees for real estate development projects,
- and in accordance with the requirements of the public interest
has decided:
For the purposes of this Decision, the following words and expressions shall have the meanings set out opposite each, unless the context requires otherwise:
State: the United Arab Emirates.
Emirate: The Emirate of Abu Dhabi.
Department: Department of Municipalities and Transport.
Centre: Abu Dhabi Real estate Centre.
Director General: Director General of the Centre.
Law: Abu Dhabi Law No. 3 of 2015, as referred to, and its amendments, and its implementing regulations.
Developer: The main Developer or sub-Developer.
Account Administrator: The bank, financial institution or other financial entity authorised by the Department to manage the escrow account in accordance with the provisions of the Law.
Bank Guarantee: A written guarantee issued by a local bank or financial institution licensed in the State, submitted by the Developer to the Centre for the purpose of authorising disbursement from the escrow account prior to the completion of 20% of the construction works for the real estate development project, in accordance with the regulations and conditions set out in this decision.
Estimated Value: The estimated value that may be determined as the preliminary Estimated Value of the total construction and building works of the project for the purposes of applying the provisions of this Decision, in accordance with the report issued by an engineering office accredited by the Centre.
For the purposes of applying the provisions of Clause (3) of Article 19 of Abu Dhabi Law No. 3 of 2015 referred to, the Centre shall approve the disbursement from the escrow account prior to the Developer’s completion of 20% of the construction and building works of the real estate development project, in return for the Developer providing alternative Bank Guarantees of a value determined by the Centre, provided that such value is not less than 20% of the value of the construction and building works of the project.
1. A Developer wishing to provide a Bank Guarantee must meet the following conditions:
a. They must have been registered as a Developer in the Emirate for a period of not less than four (4) years from the date of application, and their licence must be valid at the time of application.
b. The Developer or any of its subsidiaries must have completed and handed over at least three (3) property development projects in the Emirate of Abu Dhabi before or within the specified timeframe, provided that the delay in one or more of these projects was not due to reasons beyond its control.
c. The applicant must not have been subject to any administrative violations or penalties under the Law during a period of not less than 12 months prior to the date of application.
d. Any other conditions specified by the Centre.
2. Any Developer may be exempted from any of the conditions specified in Clause (1) above, as the Director of the Department deems appropriate.
1. The Developer shall submit an application to the Centre requesting the replacement of the prescribed percentage of completion with a Bank Guarantee, and such application shall be accompanied by the following documents:
a. Details of the completion status of projects carried out in the Emirate of Abu Dhabi and other Emirates, if any.
b. The payment schedule set out in the off-plan sales contracts for the project.
c. A detailed Statement confirming that the amounts deposited in the escrow account correspond to the payments made under the off-plan sales contracts registered in the first register on the date of application.
d. A technical report issued by an engineering firm accredited by the Centre, specifying the estimated value of the construction and building works for the project.
e. Any other documents requested by the Centre.
1. The Bank Guarantee provided by the Developer for the purposes of this Decision must meet the following conditions and requirements:
a. It must be issued by a local bank or financial institution licensed in the State and approved by the Centre for this purpose.
b. The value of the Bank Guarantee must not be less than 20% of the total cost of the project’s construction works, as per an engineering report issued by one of the engineering firms approved by the Centre, provided that the report was issued no more than thirty (30) days prior to the date of submission of the application.
c. It must be immediately liquidatable and payable in full or in part upon the first request by the Department or the Centre, either by crediting it to the escrow account or by any other method of payment determined by the Centre, without the need to consult the Developer, the guaranteeing bank or any third party.
d. Neither the Developer, the guarantor bank nor any third party may refuse, restrict or delay payment of the guaranteed amount, or object to it for any reason whatsoever.
e. It shall not be subject to any condition, restriction or time limit, nor shall it be subject to any deductions, fees or taxes payable to the Department and/or the Centre, and it shall not be revocable by the Developer, any other person or the guaranteeing bank, and shall remain valid for as long as necessary for the purpose for which it was provided.
f. The form of the guarantee shall be in accordance with the form attached to this decision.
g. Any other conditions specified by the Centre.
2. If the Bank Guarantee is issued based on the Estimated Value of the construction works as per the engineering report referred to in Clause (1) above, and it is subsequently established by a subsequent engineering report or by any other means that the Estimated Value differs significantly from the final cost as assessed by the Centre, the Developer shall provide an additional Bank Guarantee...