Guide to Calculating Property Developers’ Percentages of Completion for Property Units

Status

In force

Issuing Authority

Dubai Land Department

Effective date

XX.XX.XXXX

Official Link

https://

Land Administration

Date of issue: 28 February 2022

  1. Introduction … 4
  2. Definitions … 4
  3. Objectives of the guide … 5
  4. Key responsibilities … 5
  5. Basis for calculating the percentage of completion … 6
  6. Quantifiable elements of the project: ... 6 a. Buildings (above ground) b. Infrastructure
  7. Types of reports … 6
  8. Areas: … 7 a. Building area b. Land area c. International Space Standards (IPMS)
  9. Project description and scope … 7
  10. The official procedure for the work … 7
  11. Outputs … 8
  12. Beneficiaries … 9

Document details

AccreditationReviewPreparation
His Excellency Sultan Butti bin MajranHis Excellency Marwan bin GhalitaMr Mohammed Khader Al-DahName
Director General of the Land DepartmentChief Executive of the Real Estate Regulatory AgencySenior Manager, Surveying Department, Register and Property Services SectorJob title

Releases

DateDocument titleEdition
17 July 2016Guidelines and Standards for Technical Reports on Project Monitoring1
1 October 2018
(Decision 191/2018)
A Guide to Calculating and Determining the Percentage of Completion for Property Development...